| Expanded Driveway | ||||
| Upgraded White cabinets | ||||
| Amendment to increase price by $2,210 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 06.30.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 05.27.2025 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 06.30.2025 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 06.30.2025 | ||
| -- | -- | Inspection (Slab) (1) 07.19.2025 | ||
| -- | -- | Inspection (Drain Tile) (0) 07.19.2025 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 08.26.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 08.26.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 08.26.2025 | ||
| -- | -- | Inspection (Framing) (1) * 08.26.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 09.11.2025 | ||
| -- | -- | Inspection (Insulation) (1) 09.04.2025 | ||
| -- | -- | Inspection (Electric Service) (0) 10.10.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 08.21.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 08.21.2025 | ||
| -- | -- | Inspection (Final HVAC) (0) 11.24.2025 | ||
| -- | -- | Inspection (Final Plumbing) (0) 11.24.2025 | ||
| -- | -- | Inspection (Final Electric) (0) 11.24.2025 | ||
| -- | -- | Inspection (Final Building) (4) * 11.24.2025 | ||