VILLAS - 501-202  ::  501 Roman Way #202
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Jan 31)    show all photos
TO DO
SR Jan 20 (14) Shower wall repair Jill will schedule it after the heat is on
UPGRADES
---
CRITICAL PATH
    House Number and Status in Window (0)      
    Order Appliances (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Sod / Seed / Landscaping (0)      
Tue    Feb 3      Inspection (Framing) (1) *       
Wed    Feb 4      Insulation (2) *       
Fri    Feb 6      Inspection (Insulation) (1)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Mon    Feb 9      Drywall (Hang) (4) *       
Fri    Feb 13      Drywall (Tape, Block, Skim, Sand) (6) *       
Mon    Feb 23      Paint 1 (1)      
    House Numbers (0)      
    Mailbox (0)      
Tue    Feb 24      Cabinet Installation (2) *       
Thu    Feb 26      Granite Installation (1) *       
Fri    Feb 27      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Wed    Mar 4      Interior Trim - Paint (1)      
Thu    Mar 5      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Tue    Mar 10      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Fri    Mar 13      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Mon    Mar 16      Set Water Meter (1) *       
Tue    Mar 17      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Fri    Mar 20      HVAC Trim Out (1) *       
Mon    Mar 23      Blower Door Test (1)      
Tue    Mar 24      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Thu    Mar 26      Paint 3 (2) *       
Mon    Mar 30      Carpet (2)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Wed    Apr 1      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Tue    Apr 7      Stain Hardwood Stairs (1) *       
Wed    Apr 8      Cleaning (1)      
Thu    Apr 9      Certificate of Occupancy (1) *       
    Keys to Settlement Agent (0)      
    Request Trash Tote From POA Manager (0)      
Fri    Apr 10      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.25.2025    
-- -- $2500 Deposit Received (0)  09.25.2025    
-- -- Association Packet Requested (0)  09.25.2025    
-- -- Association Packet Received (0)  09.25.2025    
-- -- Selections Meeting (0)  09.25.2025    
-- -- Selections Sheet Signed (0)  09.25.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2025    
-- -- Deposit For Upgrades Received (0)  09.25.2025    
-- -- Building Permit (30) *   09.25.2025    
-- -- Order Roof & Floor Trusses (1)  09.25.2025    
-- -- Order Windows & Doors (0)  09.25.2025    
-- -- Stake Out Home (1)  09.25.2025    
-- -- Excavate (2)  09.25.2025    
-- -- Inspection (Footers) (1)  09.25.2025    
-- -- Inspection (Concrete Wall) (1)  09.25.2025    
-- -- Pour Footers (1) *   09.25.2025    
-- -- Set Forms (2)  09.25.2025    
-- -- Pour Foundation Walls (1)  09.25.2025    
-- -- Plumb Slab (2)  09.25.2025    
-- -- Inspection (Plumbing Under Slab) (1)  09.25.2025    
-- -- Inspection (Conduit Under Slab) (1)  09.25.2025    
-- -- Prepare Slab (1)  09.25.2025    
-- -- Inspection (Slab) (1)  09.25.2025    
-- -- Inspection (Drain Tile) (0)  09.25.2025    
-- -- Pour Slab (1) *   09.25.2025    
-- -- Settlement Agent Confirmed (0)  09.25.2025    
-- -- Framing I (9)  09.25.2025    
-- -- Order Steps (0)  09.25.2025    
-- -- Order Tubs / Showers (0)  09.25.2025    
-- -- Framing II (8)  09.25.2025    
-- -- Framing III (8) *   09.25.2025    
-- -- Verify Window & Roof Structure (0)  09.25.2025    
-- -- Install Stairs (0) *   10.02.2025    
-- -- Windows & Doors (0) *   10.27.2025    
-- -- Roofing (0) *   09.25.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Deck (0)  10.27.2025    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- HVAC Rough In (4)  10.02.2025    
-- -- Rough In Microwave Vent (0)  10.09.2025    
-- -- Plumbing Rough In (4)  10.09.2025    
-- -- Electric Rough In (4)  01.11.2026     in process 12/3- almost completed
-- -- Inspection (Rough In HVAC) (1)  01.22.2026    
-- -- Inspection (Rough In Plumbing) (1)  02.02.2026    
-- -- Inspection (Rough In Electric) (1)  01.22.2026    
-- -- Inspection (Deck Piers) (0)  01.22.2026    
-- -- Exterior Vinyl (0) *   02.02.2026    
-- -- Exterior Stone (0)  02.02.2026    
-- -- Inspection (Electric Service) (0)  01.15.2026    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Garage Door (0)  09.25.2025    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025