| Thu | Dec 18 | House Number and Status in Window (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Gutters (0) | ||
| Thu | Dec 18 | Driveway (0) * | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Sod / Seed / Landscaping (0) | ||
| Thu | Dec 18 | Electric Rough In (4) | in process 12/3- almost completed | |
| Wed | Dec 24 | Inspection (Rough In HVAC) (1) | ||
| Thu | Dec 25 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 26 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 29 | Inspection (Framing) (1) * | ||
| Tue | Dec 30 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 30 | Exterior Vinyl (0) * | ||
| Tue | Dec 30 | Exterior Stone (0) | ||
| Tue | Dec 30 | Insulation (2) * | ||
| Thu | Jan 1 | Inspection (Insulation) (1) | ||
| Fri | Jan 2 | Inspection (Electric Service) (0) | ||
| Fri | Jan 2 | Set Electric Meter (0) * | ||
| Fri | Jan 2 | Inspection (Main Sewer Line) (0) | ||
| Fri | Jan 2 | Inspection (Main Water Line) (0) | ||
| Fri | Jan 2 | Order Interior Doors & Trim (0) | ||
| Fri | Jan 2 | Drywall (Hang) (4) * | ||
| Thu | Jan 8 | Drywall (Tape, Block, Skim, Sand) (6) * | ||
| Fri | Jan 16 | Paint 1 (1) | ||
| Mon | Jan 19 | House Numbers (0) | ||
| Mon | Jan 19 | Mailbox (0) | ||
| Mon | Jan 19 | Cabinet Installation (2) * | ||
| Wed | Jan 21 | Granite Installation (1) * | ||
| Thu | Jan 22 | Interior Trim - Install (3) * | ||
| Tue | Jan 27 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Jan 27 | Interior Trim - Paint (1) | ||
| Wed | Jan 28 | Luxury Vinyl Plank (3) * | ||
| Mon | Feb 2 | Luxury Vinyl Tile (0) | ||
| Mon | Feb 2 | Paint 2 (3) | ||
| Thu | Feb 5 | Cover Floors (1) | ||
| Fri | Feb 6 | Deliver Plumbing / Lighting Fixtures (0) | ||
| Fri | Feb 6 | Shoe Moulding (0) | ||
| Fri | Feb 6 | Shelving, Door Knobs, Fire Extinguisher (0) * | ||
| Fri | Feb 6 | Install Coded Lockbox (add extra keys) (0) | ||
| Fri | Feb 6 | Pay Water / Sewer Taps (0) | ||
| Fri | Feb 6 | Set Water Meter (0) * | ||
| Fri | Feb 6 | Electric Trim Out (3) * | ||
| Wed | Feb 11 | Ceiling Fans (0) | ||
| Wed | Feb 11 | HVAC Trim Out (1) * | ||
| Thu | Feb 12 | Blower Door Test (1) | ||
| Fri | Feb 13 | Plumbing Trim Out (2) * | ||
| Tue | Feb 17 | Install Appliances (0) * | ||
| Tue | Feb 17 | Paint 3 (2) * | ||
| Thu | Feb 19 | Carpet (2) | ||
| Mon | Feb 23 | Inspection (Final HVAC) (1) | ||
| Tue | Feb 24 | Inspection (Final Plumbing) (1) | ||
| Wed | Feb 25 | Inspection (Final Electric) (1) | ||
| Thu | Feb 26 | Inspection (Final Building) (2) * | ||
| Mon | Mar 2 | Pre Walk Through (0) | ||
| Mon | Mar 2 | Stain Hardwood Stairs (1) * | ||
| Tue | Mar 3 | Cleaning (1) | ||
| Wed | Mar 4 | Certificate of Occupancy (1) * | ||
| Thu | Mar 5 | Keys to Settlement Agent (0) | ||
| Thu | Mar 5 | Request Trash Tote From POA Manager (0) | ||
| Thu | Mar 5 | Closing (1) | ||
| Fri | Mar 6 | Remove Coded Lockbox (0) | ||
| -- | -- | Ratified Contract? (0) 09.25.2025 | ||
| -- | -- | $2500 Deposit Received (0) 09.25.2025 | ||
| -- | -- | Association Packet Requested (0) 09.25.2025 | ||
| -- | -- | Association Packet Received (0) 09.25.2025 | ||
| -- | -- | Selections Meeting (0) 09.25.2025 | ||
| -- | -- | Selections Sheet Signed (0) 09.25.2025 | ||
| -- | -- | Amendment for Upgrades (B,S,L,T,BCP) (0) 09.25.2025 | ||
| -- | -- | Deposit For Upgrades Received (0) 09.25.2025 | ||
| -- | -- | Building Permit (30) * 09.25.2025 | ||
| -- | -- | Order Roof & Floor Trusses (1) 09.25.2025 | ||
| -- | -- | Order Windows & Doors (0) 09.25.2025 | ||
| -- | -- | Stake Out Home (1) 09.25.2025 | ||
| -- | -- | Excavate (2) 09.25.2025 | ||
| -- | -- | Inspection (Footers) (1) 09.25.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.25.2025 | ||
| -- | -- | Pour Footers (1) * 09.25.2025 | ||
| -- | -- | Set Forms (2) 09.25.2025 | ||
| -- | -- | Pour Foundation Walls (1) 09.25.2025 | ||
| -- | -- | Plumb Slab (2) 09.25.2025 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 09.25.2025 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.25.2025 | ||
| -- | -- | Prepare Slab (1) 09.25.2025 | ||
| -- | -- | Inspection (Slab) (1) 09.25.2025 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.25.2025 | ||
| -- | -- | Pour Slab (1) * 09.25.2025 | ||
| -- | -- | Settlement Agent Confirmed (0) 09.25.2025 | ||
| -- | -- | Framing I (9) 09.25.2025 | ||
| -- | -- | Order Steps (0) 09.25.2025 | ||
| -- | -- | Order Tubs / Showers (0) 09.25.2025 | ||
| -- | -- | Framing II (8) 09.25.2025 | ||
| -- | -- | Framing III (8) * 09.25.2025 | ||
| -- | -- | Verify Window & Roof Structure (0) 09.25.2025 | ||
| -- | -- | Install Stairs (0) * 10.02.2025 | ||
| -- | -- | Windows & Doors (0) * 10.27.2025 | ||
| -- | -- | Roofing (0) * 09.25.2025 | ||
| -- | -- | Order Cabinets (0) 10.16.2025 | ||
| -- | -- | Deck (0) 10.27.2025 | ||
| -- | -- | Privacy Divider / Fence (0) * 09.25.2025 | ||
| -- | -- | HVAC Rough In (4) 10.02.2025 | ||
| -- | -- | Rough In Microwave Vent (0) 10.09.2025 | ||
| -- | -- | Plumbing Rough In (4) 10.09.2025 | ||
| -- | -- | Loan Approval (0) 09.25.2025 | ||
| -- | -- | Deed Preparation (0) 09.25.2025 | ||
| -- | -- | Garage Door (0) 09.25.2025 | ||
| -- | -- | Appraiser Confirms Construction Completion (0) 09.25.2025 | ||
| -- | -- | C.O. to Lender (0) 09.25.2025 | ||
| -- | -- | Schedule Closing (0) 09.25.2025 | ||
| -- | -- | Buyer Walk Through (1) * 09.25.2025 | ||
| -- | -- | Payment for Upgrades (0) 09.25.2025 | ||
| -- | -- | Review Settlement Statement (0) 09.25.2025 | ||
| -- | -- | Jerry Signs Closing Documents (0) 09.25.2025 | ||