VILLAS - 501-302  ::  501 Roman Way #302
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
CL Jan 11 (223) Test
CL Mar 12 (163) Finish drywall over the sprinkler line in kitchen 3/11
CL Apr 6 (138) pretty large blemish on cabinet to far left Fred
CL Apr 6 (138) missing brown piece missing (currently white) filler - Fred
CL May 9 (105) Countertop too small
CL May 9 (105) Does the sink need to be enforced where it’s split on the back panel? Reinforced
CL May 9 (105) Does the sink need to be enforced where it’s split on the back panel?
CL May 27 (87) Stairs being stained-not accessible 5-27
CL Jun 10 (73) Shower rod needs to be installed Tom
CL Jun 10 (73) Remove countertops
CL Jun 10 (73) Paint attic cover
CL Jun 17 (66) Is there a piece that is missing on all of the heat pumps? Or are they supposed to be open like that?
CL Jun 21 (62) Fire alarm box needs to be installed near the door Jesus
CL Jun 24 (59) Does a more permanent deadbolt plate need to be installed on the apartment doors?
CL Jun 29 (54) Few small bathtub repairs needed here Valley Tub Repair
CL Jun 29 (54) Patio set needed here
CL Jul 8 (45) Few cabinet touch ups needed
CL Jul 11 (42) Some type of stickiness located near blue tape on the kitchen cabinet
CL Jul 11 (42) Small cabinet blemish in bathroom Jill
CL Jan 11 (223) Plastic Plumbing Pipe not connected in roof was leaking water 1/10
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.25.2025    
-- -- $2500 Deposit Received (0)  09.25.2025    
-- -- Association Packet Requested (0)  09.25.2025    
-- -- Association Packet Received (0)  09.25.2025    
-- -- Selections Meeting (0)  09.25.2025    
-- -- Selections Sheet Signed (0)  09.25.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2025    
-- -- Deposit For Upgrades Received (0)  09.25.2025    
-- -- Building Permit (30) *   09.25.2025    
-- -- Order Roof & Floor Trusses (0)  09.25.2025    
-- -- Order Windows & Doors (0)  09.25.2025    
-- -- Stake Out Home (1)  09.25.2025    
-- -- Excavate (2)  09.25.2025    
-- -- Inspection (Footers) (1)  09.25.2025    
-- -- Pour Footers (1) *   09.25.2025    
-- -- Set Forms (2)  09.25.2025    
-- -- Inspection (Concrete Wall) (1)  09.25.2025    
-- -- Pour Foundation Walls (1)  09.25.2025    
-- -- Plumb Slab (2)  09.25.2025    
-- -- Inspection (Plumbing Under Slab) (1)  09.25.2025    
-- -- Inspection (Conduit Under Slab) (1)  09.25.2025    
-- -- Prepare Slab (1)  09.25.2025    
-- -- Inspection (Slab) (1)  09.25.2025    
-- -- Inspection (Drain Tile) (0)  09.25.2025    
-- -- Pour Slab (1) *   09.25.2025    
-- -- Settlement Agent Confirmed (0)  09.25.2025    
-- -- Framing I (9)  09.25.2025    
-- -- Order Steps (0)  09.25.2025    
-- -- Order Tubs / Showers (0)  09.25.2025    
-- -- Framing II (8)  09.25.2025    
-- -- Framing III (8) *   09.25.2025    
-- -- Verify Window & Roof Structure (0)  09.25.2025    
-- -- Install Stairs (0) *   10.02.2025    
-- -- Windows & Doors (0) *   10.27.2025    
-- -- House Number and Status in Window (0)  05.27.2026    
-- -- Roofing (0) *   09.25.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Order Appliances (0)  05.21.2026    
-- -- Deck (0)  10.27.2025    
-- -- Gutters (0)  03.23.2026    
-- -- Driveway (0) *   02.19.2026    
-- -- Patio (0)  04.13.2026    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- Sod / Seed / Landscaping (0)  06.12.2026    
-- -- HVAC Rough In (4)  10.02.2025    
-- -- Plumbing Rough In (4)  10.09.2025    
-- -- Electric Rough In (4)  01.11.2026     in process 12/3- almost completed
-- -- Inspection (Rough In HVAC) (1)  01.22.2026    
-- -- Inspection (Rough In Plumbing) (1)  02.02.2026    
-- -- Inspection (Rough In Electric) (1)  01.22.2026    
-- -- Inspection (Framing) (1) *   02.19.2026    
-- -- Inspection (Deck Piers) (0)  01.22.2026    
-- -- Exterior Vinyl (0) *   02.02.2026    
-- -- Exterior Stone (0)  02.02.2026    
-- -- Insulation (2) *   02.19.2026    
-- -- Inspection (Insulation) (1)  02.19.2026    
-- -- Inspection (Electric Service) (0)  01.15.2026    
-- -- Set Electric Meter (0) *   04.06.2026    
-- -- Inspection (Main Sewer Line) (0)  06.11.2026    
-- -- Inspection (Main Water Line) (0)  04.14.2026    
-- -- Order Interior Doors & Trim (0)  03.30.2026    
-- -- Drywall (Hang) (4) *   02.26.2026    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   03.12.2026     In process 3/7
-- -- Paint 1 (1)  03.16.2026    
-- -- Garage Door (0)  09.25.2025    
-- -- House Numbers (0)  05.27.2026    
-- -- Mailbox (0)  06.04.2026    
-- -- Cabinet Installation (2) *   04.04.2026    
-- -- Granite Installation (1) *   05.27.2026    
-- -- Interior Trim - Install (3) *   04.23.2026     in process 4/15
-- -- Order Plumbing / Lighting Fixtures (0)  04.09.2026    
-- -- Interior Trim - Paint (1)  04.23.2026    
-- -- Luxury Vinyl Plank (3) *   05.02.2026     4/30
-- -- Luxury Vinyl Tile (0)  04.23.2026    
-- -- Paint 2 (3)  05.09.2026     in process 5/6
-- -- Cover Floors (0)  05.27.2026    
-- -- Deliver Plumbing / Lighting Fixtures (0)  05.07.2026    
-- -- Shoe Moulding (0)  05.14.2026    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   05.21.2026     In process 5/13
-- -- Install Coded Lockbox (add extra keys) (0)  06.04.2026    
-- -- Pay Water / Sewer Taps (0)  06.11.2026    
-- -- Set Water Meter (1) *   06.15.2026    
-- -- Electric Trim Out (3) *   05.18.2026     In process 5/13
-- -- Ceiling Fans (0)  05.21.2026    
-- -- HVAC Trim Out (1) *   06.04.2026    
-- -- Blower Door Test (1)  07.06.2026    
-- -- Plumbing Trim Out (2) *   06.10.2026    
-- -- Install Appliances (0) *   06.24.2026    
-- -- Paint 3 (2) *   06.24.2026    
-- -- Carpet (2)  05.18.2026    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- Inspection (Final HVAC) (0)  06.25.2026    
-- -- Inspection (Final Plumbing) (0)  06.25.2026    
-- -- Inspection (Final Electric) (0)  06.25.2026    
-- -- Inspection (Final Building) (4) *   07.15.2026    
-- -- Pre Walk Through (0)  06.25.2026    
-- -- Stain Hardwood Stairs (1) *   06.29.2026    
-- -- Cleaning (1)  06.29.2026    
-- -- Certificate of Occupancy (1) *   07.29.2026    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Keys to Settlement Agent (0)  06.25.2026    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025    
-- -- Request Trash Tote From POA Manager (0)  06.25.2026    
-- -- Closing (1)  06.25.2026    
-- -- Remove Coded Lockbox (0)  06.25.2026