| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| Tue | Feb 3 | Inspection (Concrete Wall) (1) | ||
| Wed | Feb 4 | Inspection (Plumbing Under Slab) (1) | ||
| Thu | Feb 5 | Inspection (Conduit Under Slab) (1) | ||
| Fri | Feb 6 | Inspection (Slab) (1) | ||
| Inspection (Drain Tile) (0) | ||||
| Mon | Feb 9 | Inspection (Rough In HVAC) (1) | ||
| Tue | Feb 10 | Inspection (Rough In Plumbing) (1) | ||
| Wed | Feb 11 | Inspection (Rough In Electric) (1) | ||
| Thu | Feb 12 | Inspection (Framing) (1) * | ||
| Inspection (Deck Piers) (0) | ||||
| Fri | Feb 13 | Inspection (Insulation) (1) | ||
| Inspection (Electric Service) (0) | ||||
| Inspection (Main Sewer Line) (0) | ||||
| Inspection (Main Water Line) (0) | ||||
| Inspection (Final HVAC) (0) | ||||
| Inspection (Final Plumbing) (0) | ||||
| Inspection (Final Electric) (0) | ||||
| Mon | Feb 16 | Inspection (Final Building) (4) * | ||
| TO DO - COMPLETED OR DELETED | ||||
| --- | ||||
| UPGRADES - COMPLETED | ||||
| --- | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 10.09.2025 | ||