VILLAS - 501  ::  501 Roman Way
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Jan 31)    show all photos
TO DO
Foyer Flooring - LVP Confirmed 1/19
Railing for decks Dutchway?
SR Dec 30 (35) Locks - exterior, interior, sprinkler, closets New proposal sent to Paul on 1/19
SR Jan 19 (15) Washer & Dryer Stackable with stack kit - waiting on models from Kate
SR Jan 19 (15) Paint color and sheen Benjamin Moore Alabaster White (876)
SR Jan 19 (15) Blinds White Vinyl One Inch Project Source (Tom will install)
SR Jan 19 (15) Knox Box Scott submitted order Jan 27, waiting on HFD approval
SR Jan 20 (14) Exterior building material - Hardie boards?
SR Jan 20 (14) Numbers - Building, Apartments, Storage Closets
SR Jan 22 (12) Sprinkler System Test We have City documentation of passing their test
CL Jan 29 (5) Scrape Snow for Parking Space 1/28
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Exterior Locks Game plan confirmed?
How many Type A or Type B units do we need?
SR Jan 19 (15) Storage Closet rental rates
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  12.01.2025    
-- -- $2500 Deposit Received (0)  12.01.2025    
-- -- Association Packet Requested (0)  12.01.2025    
-- -- Association Packet Received (0)  12.01.2025    
-- -- Selections Meeting (0)  12.01.2025    
-- -- Selections Sheet Signed (0)  12.01.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  12.01.2025    
-- -- Deposit For Upgrades Received (0)  12.01.2025    
-- -- Building Permit (30) *   12.01.2025    
-- -- Order Roof & Floor Trusses (1)  12.01.2025    
-- -- Order Windows & Doors (0)  12.01.2025    
-- -- Stake Out Home (1)  12.01.2025    
-- -- Excavate (2)  12.01.2025    
-- -- Inspection (Footers) (1)  12.01.2025    
-- -- Inspection (Concrete Wall) (1)  12.01.2025    
-- -- Pour Footers (1) *   12.01.2025    
-- -- Set Forms (2)  12.01.2025    
-- -- Pour Foundation Walls (1)  12.01.2025    
-- -- Plumb Slab (2)  12.01.2025    
-- -- Inspection (Plumbing Under Slab) (1)  12.01.2025    
-- -- Inspection (Conduit Under Slab) (1)  12.01.2025    
-- -- Prepare Slab (1)  12.01.2025    
-- -- Inspection (Slab) (1)  12.01.2025    
-- -- Inspection (Drain Tile) (0)  12.01.2025    
-- -- Pour Slab (1) *   12.01.2025    
-- -- Settlement Agent Confirmed (0)  12.01.2025    
-- -- Framing I (9)  12.01.2025    
-- -- Order Steps (0)  12.01.2025    
-- -- Order Tubs / Showers (0)  12.01.2025    
-- -- Framing II (8)  12.01.2025    
-- -- Framing III (8) *   12.01.2025    
-- -- Verify Window & Roof Structure (0)  12.01.2025    
-- -- Install Stairs (0) *   12.01.2025    
-- -- Windows & Doors (0) *   12.01.2025    
-- -- House Number and Status in Window (0)  12.01.2025    
-- -- Roofing (0) *   12.01.2025    
-- -- Order Cabinets (0)  12.01.2025    
-- -- Order Appliances (0)  12.01.2025    
-- -- Deck (0)  12.01.2025    
-- -- Gutters (0)  12.01.2025    
-- -- Driveway (0) *   12.01.2025    
-- -- Patio (0)  12.01.2025    
-- -- Privacy Divider / Fence (0) *   12.01.2025    
-- -- Sod / Seed / Landscaping (0)  12.01.2025    
-- -- HVAC Rough In (4)  12.01.2025    
-- -- Rough In Microwave Vent (0)  12.01.2025    
-- -- Plumbing Rough In (4)  12.01.2025    
-- -- Electric Rough In (4)  12.01.2025    
-- -- Inspection (Rough In HVAC) (1)  12.01.2025    
-- -- Inspection (Rough In Plumbing) (1)  12.01.2025    
-- -- Inspection (Rough In Electric) (1)  12.01.2025    
-- -- Inspection (Framing) (1) *   12.01.2025    
-- -- Inspection (Deck Piers) (0)  12.01.2025    
-- -- Exterior Vinyl (0) *   12.01.2025    
-- -- Exterior Stone (0)  12.01.2025    
-- -- Insulation (2) *   12.01.2025    
-- -- Inspection (Insulation) (1)  12.01.2025    
-- -- Inspection (Electric Service) (0)  12.01.2025    
-- -- Set Electric Meter (0) *   12.01.2025    
-- -- Inspection (Main Sewer Line) (0)  12.01.2025    
-- -- Inspection (Main Water Line) (0)  12.01.2025    
-- -- Order Interior Doors & Trim (0)  12.01.2025    
-- -- Drywall (Hang) (4) *   12.01.2025    
-- -- Loan Approval (0)  12.01.2025    
-- -- Deed Preparation (0)  12.01.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   12.01.2025    
-- -- Paint 1 (1)  12.01.2025    
-- -- Garage Door (0)  12.01.2025    
-- -- House Numbers (0)  12.01.2025    
-- -- Mailbox (0)  12.01.2025    
-- -- Cabinet Installation (2) *   12.01.2025    
-- -- Granite Installation (1) *   12.01.2025    
-- -- Interior Trim - Install (3) *   12.01.2025    
-- -- Order Plumbing / Lighting Fixtures (0)  12.01.2025    
-- -- Interior Trim - Paint (1)  12.01.2025    
-- -- Luxury Vinyl Plank (3) *   12.01.2025    
-- -- Luxury Vinyl Tile (0)  12.01.2025    
-- -- Paint 2 (3)  12.01.2025    
-- -- Cover Floors (0)  12.01.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  12.01.2025    
-- -- Shoe Moulding (0)  12.01.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   12.01.2025    
-- -- Install Coded Lockbox (add extra keys) (0)  12.01.2025    
-- -- Pay Water / Sewer Taps (0)  12.01.2025    
-- -- Set Water Meter (1) *   12.01.2025    
-- -- Electric Trim Out (3) *   12.01.2025    
-- -- Ceiling Fans (0)  12.01.2025    
-- -- HVAC Trim Out (1) *   12.01.2025    
-- -- Blower Door Test (1)  12.01.2025    
-- -- Plumbing Trim Out (2) *   12.01.2025    
-- -- Install Appliances (0) *   12.01.2025    
-- -- Paint 3 (2) *   12.01.2025    
-- -- Carpet (2)  12.01.2025    
-- -- Appraiser Confirms Construction Completion (0)  12.01.2025    
-- -- Inspection (Final HVAC) (0)  12.01.2025    
-- -- Inspection (Final Plumbing) (0)  12.01.2025    
-- -- Inspection (Final Electric) (0)  12.01.2025    
-- -- Inspection (Final Building) (4) *   12.01.2025    
-- -- Pre Walk Through (0)  12.01.2025    
-- -- Stain Hardwood Stairs (1) *   12.01.2025    
-- -- Cleaning (1)  12.01.2025    
-- -- Certificate of Occupancy (1) *   12.01.2025    
-- -- C.O. to Lender (0)  12.01.2025    
-- -- Schedule Closing (0)  12.01.2025    
-- -- Buyer Walk Through (1) *   12.01.2025    
-- -- Payment for Upgrades (0)  12.01.2025    
-- -- Keys to Settlement Agent (0)  12.01.2025    
-- -- Review Settlement Statement (0)  12.01.2025    
-- -- Jerry Signs Closing Documents (0)  12.01.2025    
-- -- Request Trash Tote From POA Manager (0)  12.01.2025    
-- -- Closing (1)  12.01.2025    
-- -- Remove Coded Lockbox (0)  12.01.2025