CONGERS-3 - 42  ::  1605 Palomino Trail
[ BUILD: 20241825 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
There is a different shower in this house. Correct?
Concrete patching needed in rear of home or will grading cover?
Bottom piece of shiplap is missing. Floor appears to be uneven, does George know how to fix that?
Cover hardwood treads leading to main level
All doors are missing middle hinge. Hinges installed are gold that has been painted white.
There appears to be a framing board sticking out the drywall in the hall bathroom Tom
Trim out garage
Semi gloss paint from the crown molding got on the ceiling quite a bit. Ceilings are likely going to have to be repainted to cover up. Jesus
Black drain in hall bath needs to be installed Mazur
Light switch cover needed to back patio
Light switch covers needed in multiple places Electrician
Trade out WHITE
Trade out white electrical receptacles on kitchen island brown or black
Lots of lightbulbs needed Electrician
Does the light fixture in the bonus room get a cover of some sort? Or maybe we need different lightbulbs?
I do not see a refrigerator in this unit either
Lots of garage trim is loose here Buddy
Large oil spill on driveway Power wash - Buddy
This shower has a very small edge to avoid water leaking out. The standard shower is significantly deeper. Do we need to do anything additionally?
CODED LOCKBOX 4242
Push nails in back of deck board below door
Home inspection - Mon, Apr 28 at
Home inspection - Mon, Apr 28 at 10am
Home inspection - Mon, Apr 28 at 9am
Lots of drywall glue spilled in bonus bathtub Drywaller Tim
Some pretty large cracks in the garage floor
Can we patch the cracks on the painted steps and paint another coat? Jesus. In process 5/7
Final touchups needed on a few spots in the ceilings that have been patched Jesus
Install window screens Jill
Bonus bathroom caulk in side splash Jesus
Cock replace shoe molded bathtub, and bonus bath
Patch, sand, and paint next to light switch in bonus bath Jesus
Lots of scratches on oak treads to main level Jesus
Nail hole at transition strip on stairs to hallway in living room Tom will fill these
Shiplap and crown molding look amazing!!!
Patch and paint light fixture headed up second set of steps Jesus
Cover media box under stairs Tom
Electrical outlets on island are not fixed to cabinet Electrician
Caulk the shoe mold at bonus bath Jesus
Gap on deck boards Buddy
Strap wires in island Electrician
Furnaxe wire needs strapping
FIll gap between drywall and switch cover in bonus bathroom Jesus
Fill hole in garage door ceiling Jesus
Furnace wire needs strapping Mast and Brunk
Screw in nails on the back trim White board under outside of exterior door to dining room
The door going into the bonus bathroom is very crooked Jorge
Patch and paint drywall seams on kitchen ceiling Jesus
Patch and paint drywall in living room next to far right inside can light Jesus
Patch and paint drywall seams under second floor stairwell Jesus
Patch and paint nail pops on railing side of stairwell leading from 1st to 2nd floor, below railing Jesus
Patch and paint holes at wall switches at bottom of 2nd floor stairwell Jesus
Patch and paint holes at wall switches at first floor bathroom Jesus
Chip in bath tub Afternoon of May 8
Touchup cleaning from painters repairs Lynn
Paint touchup throughout Jesus
Light switch cover needed in bonus bathroom Jill
Large drywall repair in stairwell Tom, Jesus
Remove paint drips in master bathroom Jesus
Curved wall on stairwell Jesus
scratches on upper kitchen cabinets Fred - installed week of June 9 (Wed, Thu)
remove paint from LVT and LVP Jesus
remove plastic from DW
reclean cabinets of dust adn clean inside trashcan Lynn
power wash front of house Jill- will be done 6/5
remove trash and sweep driveway Jill
hang fire extinguisher
clean ss sink Lynn
spray for ants on deck- may be nesting in door trim Jill
address flashing underneath deck door Tom
replace deck board
recaulk pedestal sink at wall Jesus
fill nail holes at bonus bath shoe in front of tub Jesus
remove gravel frmo backyard and sod Pettit
garage door not operating Jill, Jeff
remove black scuff mark frmo corner of island Lynn
Closing delayed because of appraisal error
Fix flooring bonus bath Denny
Put door back on bonus bath
Sod needed
reclean surfaces and floors after punch is completed. Lynn
Pressure wash front of house
Remove yellow cover from smoke detector Jill
Final cleaning
Clean up a few things in the garage Jill
Julie Hamann, 540-246-7922
I do not think the heat pump is functioning correctly. It’s set to 72 and a 78 in the house. Outside unit is not running
Cabinet doors? to be fixed on Jul 22 - Jill will provide access to Fred
Mirror? Joe
UPGRADES - COMPLETED
    Finished room behind garage  
    Finished Full Bath in Bonus Room  
    Expanded 12 x 18 Deck  
    Level 3 Quartz in Kitchen  
    Double Pull Out Trash Can  
    Expanded Driveway  
    4" Crown Moulding on Main Level  
    ShipLap on Living Room Wall  
    Digital Deadbolt  
    Amendment to increase price by $25,900  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  11.13.2024    
-- -- $2500 Deposit Received (0)  11.20.2024    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  11.16.2024    
-- -- Selections Meeting (0)  12.31.2024    
-- -- Selections Sheet Signed (0)  01.06.2025     12/30: sent to Julie
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  01.23.2025     1/5: Sent to Julie
-- -- Deposit For Upgrades Received (0)  01.22.2025    
-- -- Building Permit (30) *   10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Order Windows & Doors (0)  12.02.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1) *   10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.24.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.24.2024    
-- -- Prepare Slab (1)  11.24.2024    
-- -- Inspection (Slab) (1)  12.02.2024    
-- -- Inspection (Drain Tile) (0)  12.02.2024    
-- -- Pour Slab (1) *   12.02.2024    
-- -- Settlement Agent Confirmed (0)  01.24.2025     1/23: sent to Brittany
-- -- Framing I (9)  12.19.2024    
-- -- Order Steps (0)  01.16.2025    
-- -- Order Tubs / Showers (0)  01.23.2025    
-- -- Framing II (8)  12.28.2024    
-- -- Framing III (8) *   01.13.2025    
-- -- Verify Window & Roof Structure (0)  01.16.2025    
-- -- Install Stairs (0) *   01.16.2025    
-- -- Windows & Doors (0) *   01.23.2025    
-- -- House Number and Status in Window (0)  01.29.2025    
-- -- Roofing (0) *   02.02.2025    
-- -- Order Cabinets (0)  01.23.2025    
-- -- Order Appliances (0)  02.20.2025     200509352240380141
-- -- Deck (0)  03.28.2025    
-- -- Gutters (0)  03.19.2025    
-- -- Driveway (0) *   04.06.2025    
-- -- Patio (0)  03.15.2025    
-- -- Privacy Divider / Fence (0) *   04.06.2025    
-- -- Sod / Seed / Landscaping (0)  08.07.2025    
-- -- HVAC Rough In (4)  01.25.2025     in process 1/22
-- -- Rough In Microwave Vent (0)  01.25.2025    
-- -- Plumbing Rough In (4)  01.25.2025     In process 1/25
-- -- Electric Rough In (4)  01.30.2025     In process 1/29
-- -- Inspection (Rough In HVAC) (1)  02.01.2025    
-- -- Inspection (Rough In Plumbing) (1)  02.01.2025    
-- -- Inspection (Rough In Electric) (1)  02.01.2025    
-- -- Inspection (Framing) (1) *   02.01.2025    
-- -- Inspection (Deck Piers) (0)  02.20.2025    
-- -- Exterior Vinyl (0) *   03.15.2025    
-- -- Exterior Stone (0)  04.14.2025     in process 4/9
-- -- Insulation (2) *   02.03.2025     In process 2/1
-- -- Inspection (Insulation) (1)  02.08.2025    
-- -- Inspection (Electric Service) (0)  02.20.2025    
-- -- Set Electric Meter (0) *   04.09.2025    
-- -- Inspection (Main Sewer Line) (0)  02.20.2025    
-- -- Inspection (Main Water Line) (0)  02.20.2025    
-- -- Order Interior Doors & Trim (0)  02.20.2025     TOM- Need LR SHIPLAP and main level crown molding
-- -- Drywall (Hang) (4) *   02.08.2025     Stocked 2/5
-- -- Loan Approval (0)  05.01.2025     Capital First Mortgage (75% LTV)
-- -- Deed Preparation (0)  03.24.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.16.2025     In process 2/12
-- -- Paint 1 (1)  02.26.2025    
-- -- Garage Door (0)  03.19.2025    
-- -- House Numbers (0)  04.28.2025    
-- -- Mailbox (0)  04.16.2025    
-- -- Cabinet Installation (2) *   02.26.2025     Thu, Feb 20
-- -- Granite Installation (1) *   03.05.2025    
-- -- Interior Trim - Install (3) *   03.12.2025     In process 3/8
-- -- Order Plumbing / Lighting Fixtures (0)  03.24.2025    
-- -- Interior Trim - Paint (1)  03.15.2025    
-- -- Luxury Vinyl Plank (3) *   03.26.2025     In process 3/21
-- -- Luxury Vinyl Tile (0)  03.26.2025     In process 3/21
-- -- Paint 2 (3)  03.12.2025    
-- -- Cover Floors (0)  04.27.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.24.2025    
-- -- Shoe Moulding (0)  04.06.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.16.2025     In process 4/9
-- -- Install Coded Lockbox (add extra keys) (0)  04.21.2025    
-- -- Pay Water / Sewer Taps (0)  03.27.2025    
-- -- Set Water Meter (1) *   04.14.2025    
-- -- Electric Trim Out (3) *   04.16.2025     In process 4/6
-- -- Ceiling Fans (0)  04.16.2025    
-- -- HVAC Trim Out (1) *   04.16.2025    
-- -- Blower Door Test (1)  05.06.2025     Monday, May 5th at 4pm
-- -- Plumbing Trim Out (2) *   03.28.2025     In process 3/26
-- -- Install Appliances (0) *   04.27.2025     Oven has been installed. Microwave and dishwasher are in dining room.
-- -- Paint 3 (2) *   04.27.2025    
-- -- Carpet (2)  04.14.2025    
-- -- Appraiser Confirms Construction Completion (0)  05.27.2025    
-- -- Inspection (Final HVAC) (0)  05.08.2025     Tuesday, May 6
-- -- Inspection (Final Plumbing) (0)  05.08.2025    
-- -- Inspection (Final Electric) (0)  05.08.2025    
-- -- Inspection (Final Building) (4) *   05.08.2025    
-- -- Pre Walk Through (0)  04.28.2025    
-- -- Stain Hardwood Stairs (1) *   04.27.2025     In process 4/19
-- -- Cleaning (1)  05.10.2025     Almost completed 5/7
-- -- Certificate of Occupancy (1) *   05.09.2025    
-- -- C.O. to Lender (0)  05.09.2025    
-- -- Schedule Closing (0)  06.09.2025    
-- -- Buyer Walk Through (1) *   05.10.2025     Thursday 4 PM
-- -- Payment for Upgrades (0)  05.05.2025    
-- -- Keys to Settlement Agent (0)  05.05.2025    
-- -- Review Settlement Statement (0)  05.11.2025    
-- -- Jerry Signs Closing Documents (0)  06.09.2025    
-- -- Request Trash Tote From POA Manager (0)  05.08.2025    
-- -- Closing (1)  06.11.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  07.03.2025