| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finished room behind garage | ||||
| Finished Full Bath in Bonus Room | ||||
| Expanded 12 x 18 Deck | ||||
| Level 3 Quartz in Kitchen | ||||
| Double Pull Out Trash Can | ||||
| Expanded Driveway | ||||
| 4" Crown Moulding on Main Level | ||||
| ShipLap on Living Room Wall | ||||
| Digital Deadbolt | ||||
| Amendment to increase price by $25,900 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 10.21.2024 | ||
| -- | -- | Inspection (Concrete Wall) (1) 10.21.2024 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 11.24.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 11.24.2024 | ||
| -- | -- | Inspection (Slab) (1) 12.02.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 12.02.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 02.01.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 02.01.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 02.01.2025 | ||
| -- | -- | Inspection (Framing) (1) * 02.01.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 02.20.2025 | ||
| -- | -- | Inspection (Insulation) (1) 02.08.2025 | ||
| -- | -- | Inspection (Electric Service) (0) 02.20.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 02.20.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 02.20.2025 | ||
| -- | -- | Inspection (Final HVAC) (0) 05.08.2025 | Tuesday, May 6 | |
| -- | -- | Inspection (Final Plumbing) (0) 05.08.2025 | ||
| -- | -- | Inspection (Final Electric) (0) 05.08.2025 | ||
| -- | -- | Inspection (Final Building) (4) * 05.08.2025 | ||