CONGERS-3 - 10  ::  1363 Derby Drive
[ BUILD: 20250712 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Jan 31)    show all photos
TO DO
CL Jan 25 (9) CODED LOCKBOX 1010
CL Jan 28 (6) Touchup paint and caulk needed on shoe molding throughout Jesus
SR Jan 8 (26) Install kick plate and shoe mold for bonus vanity Jorge (Quill)
CL Jan 24 (10) Utility room door will need to be painted Jesus
CL Jan 28 (6) Two door knobs are missing in the bonus room Paul
CL Jan 31 (3) Paint front door Jesus
CL Jan 31 (3) Drywall repair near outlet and bonus room Jesus
CL Jan 31 (3) Hinge missing on door to bonus bath Jesus
CL Jan 31 (3) Shower rod needed in bonus bath Paul
CL Jan 31 (3) Lots of touchup paint and caulking needed in bonus bathroom trim Jesus
CL Jan 31 (3) Flooring does not quite reach the shoe mold in bonus room near bathroom Denny
CL Jan 31 (3) Make sure that paint is removed from hinges. Orie of hinges are covered with white paint throughout. Jesus
CL Jan 28 (6) Brown outlet covers Kitchen island, Jill
CL Jan 31 (3) Some patching and touchup paint is needed in the primary bedroom Jesus
UPGRADES
    Stained hardwood steps to the bedroom level  
CRITICAL PATH
    Privacy Divider / Fence (0) *       
    Sod / Seed / Landscaping (0)      
    Mailbox (0)      
Tue    Feb 3      Shelving, Door Knobs, Fire Extinguisher (1) *        Bath accessories installed and handles. No shelving or mirrors 1/28
    Appraiser Confirms Construction Completion (0)       Johnny Hensley - tell when ready
Wed    Feb 4      Inspection (Final Building) (4) *        Fri, Jan 30
    Pre Walk Through (0)      
Tue    Feb 10      Stain Hardwood Stairs (1) *       
Wed    Feb 11      Cleaning (1)      
Thu    Feb 12      Certificate of Occupancy (1) *       
    C.O. to Lender (0)      
    Schedule Closing (0)       Rate lock expires January 14
Fri    Feb 13      Buyer Walk Through (1) *       
    Payment for Upgrades (0)      
    Review Settlement Statement (0)      
    Jerry Signs Closing Documents (0)      
Mon    Feb 16      Closing (1)       Brittany @ West View Title
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
Water line to refrigerator Make sure it shows up. It’s here 10/8
Patio out back or deck? Which will it be?
Back right main level wall - nails that missed corner stud Tom fixing 10/29
Is the basement bathtub supposed to be hooked up to plumbing or just set in the back unfinished bathroom? It is currently not hooked up but sitting in the garage.
Drywall stocked 10/ 31
Farmsink ordered 11/3
Bonus Room & Bathroom = Now Will Be Finished
Finish bonus room and bathroom
Bonus room needs all patched in the concrete from the shower
I do not see the farmhouse sink on site here
Cabinet installation is still in process
Bonus Bathroom Vanity needs installed
Game plan for incorrect cabinets?
SR Jan 4 (30) Secure back panel of kitchen island TJ
CL Jan 7 (27) Quite a bit of trim missing in bonus room and a door Jorge
CL Jan 7 (27) Handles missing on bonus vanity and front trim
CL Jan 7 (27) Hardware missing on coffee bar
CL Jan 7 (27) Free 3 drawer stack
CL Jan 7 (27) Large gap at pantry cabinet near wall
SR Jan 8 (26) Install kick plate at kitchen base cabinet next to pantry
SR Jan 4 (30) Bonus bathroom countertop needs to be secured Jesus
CL Jan 7 (27) Side splash needs installed bonus vanity Jesus
SR Jan 8 (26) Install handles for bonus room vanity Jill, Tom - drill holes
CL Jan 21 (13) Self closing hinge needed here Jorge
CL Jan 28 (6) Lightbulbs needed, and quite a few places Electrician, Jill
CL Jan 7 (27) No trash can in kitchen On order, Fred
SR Jan 8 (26) Remove coffee bar - incorrect color Tom
CL Jan 21 (13) Top drawer of the trashcan does not seem to be closing correctly Fred, Tom
CL Jan 24 (10) Microwave vent not working 1/24 Tom
CL Jan 24 (10) Bottom drawer of 3 drawer stack isn’t closing properly Fred, Tom
CL Jan 28 (6) Silver dining room light needs to be switched out for black? Jill, Electrician
SR Jan 12 (22) Cracked window in upper sash of primary bathroom Tom
UPGRADES - COMPLETED
    LVP bonus room  
    Expanded driveway  
    Salinas White level three granite countertops  
    Coffee bar stained cabinet with glass shelving and crown molding and level three granite  
    Farmhouse sink  
    Double pull out trashcan and island  
    Microwave vented into the exterior  
    Farmhouse style plumbing package  
    Luxury vinyl plank in upstairs hallway and bedrooms  
    Additional ceiling fan in living room  
    Digital deadbolt  
    Finished Bonus Room Behind Garage (carpet, closet)  
    Finished Full Bathroom In Bonus Room (luxury vinyl tile, 24" vanity)  
    Amendment to increase price by $26,120  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  03.20.2025    
-- -- $2500 Deposit Received (0)  03.25.2025    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  04.01.2025    
-- -- Selections Meeting (0)  04.18.2025    
-- -- Selections Sheet Signed (0)  04.22.2025     4/17: sent to Keenan
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.08.2025     11/6: new version send to buyers
-- -- Deposit For Upgrades Received (0)  04.28.2025    
-- -- Building Permit (30) *   04.11.2025    
-- -- Order Roof & Floor Trusses (1)  08.04.2025    
-- -- Order Windows & Doors (0)  09.15.2025    
-- -- Stake Out Home (1)  05.27.2025    
-- -- Excavate (2)  05.27.2025    
-- -- Inspection (Footers) (1)  07.31.2025    
-- -- Inspection (Concrete Wall) (1)  05.27.2025    
-- -- Pour Footers (1) *   05.27.2025    
-- -- Set Forms (2)  05.27.2025    
-- -- Pour Foundation Walls (1)  05.27.2025    
-- -- Plumb Slab (2)  07.31.2025    
-- -- Inspection (Plumbing Under Slab) (1)  07.31.2025    
-- -- Inspection (Conduit Under Slab) (1)  07.31.2025    
-- -- Prepare Slab (1)  07.31.2025    
-- -- Inspection (Slab) (1)  07.31.2025    
-- -- Inspection (Drain Tile) (0)  09.28.2025    
-- -- Pour Slab (1) *   07.31.2025    
-- -- Settlement Agent Confirmed (0)  05.07.2025    
-- -- Framing I (9)  09.04.2025    
-- -- Order Steps (0)  09.15.2025    
-- -- Order Tubs / Showers (0)  09.28.2025    
-- -- Framing II (8)  09.17.2025    
-- -- Framing III (8) *   09.25.2025    
-- -- Verify Window & Roof Structure (0)  09.28.2025    
-- -- Install Stairs (0) *   09.28.2025    
-- -- Windows & Doors (0) *   09.28.2025    
-- -- House Number and Status in Window (0)  10.15.2025    
-- -- Roofing (0) *   09.28.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Order Appliances (0)  10.24.2025     Kate will order 11/15 for 12/15 install
-- -- Deck (0)  01.04.2026    
-- -- Gutters (0)  12.06.2025    
-- -- Driveway (0) *   11.19.2025    
-- -- Patio (0)  01.10.2026    
-- -- HVAC Rough In (4)  09.28.2025    
-- -- Rough In Microwave Vent (0)  10.01.2025    
-- -- Plumbing Rough In (4)  10.08.2025    
-- -- Electric Rough In (4)  10.19.2025     In process 10/15
-- -- Inspection (Rough In HVAC) (1)  10.21.2025    
-- -- Inspection (Rough In Plumbing) (1)  10.21.2025    
-- -- Inspection (Rough In Electric) (1)  10.21.2025    
-- -- Inspection (Framing) (1) *   10.21.2025    
-- -- Inspection (Deck Piers) (0)  12.22.2025    
-- -- Exterior Vinyl (0) *   12.04.2025    
-- -- Exterior Stone (0)  12.04.2025    
-- -- Insulation (2) *   10.22.2025    
-- -- Inspection (Insulation) (1)  10.30.2025    
-- -- Inspection (Electric Service) (0)  10.30.2025    
-- -- Set Electric Meter (0) *   12.01.2025    
-- -- Inspection (Main Sewer Line) (0)  10.30.2025    
-- -- Inspection (Main Water Line) (0)  10.30.2025    
-- -- Order Interior Doors & Trim (0)  12.01.2025    
-- -- Drywall (Hang) (4) *   11.03.2025    
-- -- Loan Approval (0)  01.10.2026     Jodee @ United (Conventional)
-- -- Deed Preparation (0)  01.08.2026    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   12.03.2025     In process 11/28
-- -- Paint 1 (1)  12.03.2025    
-- -- Garage Door (0)  01.08.2026    
-- -- House Numbers (0)  01.23.2026    
-- -- Cabinet Installation (2) *   01.04.2026     In process 12/17
-- -- Granite Installation (1) *   01.20.2026     Tue, Jan 20
-- -- Interior Trim - Install (3) *   01.07.2026     In process 12/20
-- -- Order Plumbing / Lighting Fixtures (0)  12.22.2025    
-- -- Interior Trim - Paint (1)  01.07.2026    
-- -- Luxury Vinyl Plank (3) *   01.07.2026    
-- -- Luxury Vinyl Tile (0)  01.07.2026    
-- -- Paint 2 (3)  01.21.2026     In process 1/14
-- -- Cover Floors (0)  01.31.2026    
-- -- Deliver Plumbing / Lighting Fixtures (0)  12.22.2025    
-- -- Shoe Moulding (0)  01.14.2026     In process 1/7
-- -- Install Coded Lockbox (add extra keys) (0)  01.25.2026    
-- -- Pay Water / Sewer Taps (0)  01.11.2026    
-- -- Set Water Meter (1) *   01.12.2026    
-- -- Electric Trim Out (3) *   01.30.2026     In process 1/28. 3rd floor left to do
-- -- Ceiling Fans (0)  01.28.2026    
-- -- HVAC Trim Out (1) *   01.21.2026    
-- -- Blower Door Test (1)  01.30.2026    
-- -- Plumbing Trim Out (2) *   01.30.2026     In process. Toilets installs 1/17
-- -- Install Appliances (0) *   01.26.2026     In process - 1/21
-- -- Paint 3 (2) *   01.28.2026    
-- -- Carpet (2)  01.14.2026    
-- -- Inspection (Final HVAC) (0)  01.30.2026    
-- -- Inspection (Final Plumbing) (0)  01.30.2026    
-- -- Inspection (Final Electric) (0)  01.30.2026    
-- -- Keys to Settlement Agent (0)  01.27.2026    
-- -- Request Trash Tote From POA Manager (0)  01.27.2026