| TO DO | ||||
| UPGRADES | ||||
| Stained hardwood steps to the bedroom level | ||||
| CRITICAL PATH | ||||
| Tue | Feb 3 | Inspection (Final Building) (4) * | Fri, Jan 30 | |
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| LVP bonus room | ||||
| Expanded driveway | ||||
| Salinas White level three granite countertops | ||||
| Coffee bar stained cabinet with glass shelving and crown molding and level three granite | ||||
| Farmhouse sink | ||||
| Double pull out trashcan and island | ||||
| Microwave vented into the exterior | ||||
| Farmhouse style plumbing package | ||||
| Luxury vinyl plank in upstairs hallway and bedrooms | ||||
| Additional ceiling fan in living room | ||||
| Digital deadbolt | ||||
| Finished Bonus Room Behind Garage (carpet, closet) | ||||
| Finished Full Bathroom In Bonus Room (luxury vinyl tile, 24" vanity) | ||||
| Amendment to increase price by $26,120 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 07.31.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 05.27.2025 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 07.31.2025 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 07.31.2025 | ||
| -- | -- | Inspection (Slab) (1) 07.31.2025 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.28.2025 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 10.21.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 10.21.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 10.21.2025 | ||
| -- | -- | Inspection (Framing) (1) * 10.21.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 12.22.2025 | ||
| -- | -- | Inspection (Insulation) (1) 10.30.2025 | ||
| -- | -- | Inspection (Electric Service) (0) 10.30.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 10.30.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 10.30.2025 | ||
| -- | -- | Inspection (Final HVAC) (0) 01.30.2026 | ||
| -- | -- | Inspection (Final Plumbing) (0) 01.30.2026 | ||
| -- | -- | Inspection (Final Electric) (0) 01.30.2026 | ||