| TO DO | ||||
| UPGRADES | ||||
| Expanded Driveway | ||||
| LVP in Upstairs Hallway and Bedrooms | ||||
| Painted Steps to Bedroom Level | ||||
| Eggshell Paint | ||||
| CRITICAL PATH | ||||
| Inspection (Final HVAC) (0) | ||||
| Inspection (Final Plumbing) (0) | ||||
| Inspection (Final Electric) (0) | ||||
| Tue | Feb 3 | Inspection (Final Building) (4) * | ||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Amendment to increase price by $6,020 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 06.02.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 08.25.2025 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 08.25.2025 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 08.25.2025 | ||
| -- | -- | Inspection (Slab) (1) 08.25.2025 | ||
| -- | -- | Inspection (Drain Tile) (0) 08.25.2025 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 11.10.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 11.10.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 11.10.2025 | ||
| -- | -- | Inspection (Framing) (1) * 11.10.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 01.04.2026 | ||
| -- | -- | Inspection (Insulation) (1) 11.20.2025 | ||
| -- | -- | Inspection (Electric Service) (0) 12.06.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 08.18.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 08.18.2025 | ||