VILLAS - 501-201  ::  501 Roman Way #201
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Sunday (Jun 28)    show all photos
TO DO
---
UPGRADES
---
CRITICAL PATH
Wed    Jul 1      Inspection (Final Building) (4) *       
Tue    Jul 7      Certificate of Occupancy (1) *       
TO DO - COMPLETED OR DELETED
SR Mar 5 (118) Gypcrete - Mar 25
SR Apr 20 (72) Smelly bathroom
CL May 9 (53) Few countertop issues as far as fitting the space
CL Jun 10 (21) Second and third floor units need to have board painted under washing machine Jesus
CL Jun 13 (18) Weatherstripping needed on door here
CL Jun 17 (14) I feel like there’s a bottom piece of the dishwasher that is missing. It’s actually located inside the dishwasher. Is there a reason that we cannot install? Jill
CL Jun 21 (10) Does the HVAC unit need some type of cover on it?
CL Jun 21 (10) Board under washing machine needs to be painted
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.25.2025    
-- -- $2500 Deposit Received (0)  09.25.2025    
-- -- Association Packet Requested (0)  09.25.2025    
-- -- Association Packet Received (0)  02.09.2026    
-- -- Selections Meeting (0)  09.25.2025    
-- -- Selections Sheet Signed (0)  09.25.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2025    
-- -- Deposit For Upgrades Received (0)  09.25.2025    
-- -- Building Permit (30) *   09.25.2025    
-- -- Order Roof & Floor Trusses (1)  09.25.2025    
-- -- Order Windows & Doors (0)  09.25.2025    
-- -- Stake Out Home (1)  09.25.2025    
-- -- Excavate (2)  09.25.2025    
-- -- Inspection (Footers) (1)  09.25.2025    
-- -- Inspection (Concrete Wall) (1)  09.25.2025    
-- -- Pour Footers (1) *   09.25.2025    
-- -- Set Forms (2)  09.25.2025    
-- -- Pour Foundation Walls (1)  09.25.2025    
-- -- Plumb Slab (2)  09.25.2025    
-- -- Inspection (Plumbing Under Slab) (1)  09.25.2025    
-- -- Inspection (Conduit Under Slab) (1)  09.25.2025    
-- -- Prepare Slab (1)  09.25.2025    
-- -- Inspection (Slab) (1)  09.25.2025    
-- -- Inspection (Drain Tile) (0)  09.25.2025    
-- -- Pour Slab (1) *   09.25.2025    
-- -- Settlement Agent Confirmed (0)  09.25.2025    
-- -- Framing I (9)  09.25.2025    
-- -- Order Steps (0)  09.25.2025    
-- -- Order Tubs / Showers (0)  09.25.2025    
-- -- Framing II (8)  09.25.2025    
-- -- Framing III (8) *   09.25.2025    
-- -- Verify Window & Roof Structure (0)  09.25.2025    
-- -- Install Stairs (0) *   10.02.2025    
-- -- Windows & Doors (0) *   10.27.2025    
-- -- House Number and Status in Window (0)  06.04.2026    
-- -- Roofing (0) *   09.25.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Order Appliances (0)  05.21.2026    
-- -- Deck (0)  10.27.2025    
-- -- Gutters (0)  03.23.2026    
-- -- Driveway (0) *   02.19.2026    
-- -- Patio (0)  04.13.2026    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- Sod / Seed / Landscaping (0)  06.12.2026    
-- -- HVAC Rough In (4)  10.02.2025    
-- -- Rough In Microwave Vent (0)  10.09.2025    
-- -- Plumbing Rough In (4)  10.09.2025    
-- -- Electric Rough In (4)  01.11.2026     in process 12/3- almost completed
-- -- Inspection (Rough In HVAC) (1)  01.22.2026    
-- -- Inspection (Rough In Plumbing) (1)  02.02.2026    
-- -- Inspection (Rough In Electric) (1)  01.22.2026    
-- -- Inspection (Framing) (1) *   02.19.2026    
-- -- Inspection (Deck Piers) (0)  01.22.2026    
-- -- Exterior Vinyl (0) *   02.02.2026    
-- -- Exterior Stone (0)  02.02.2026    
-- -- Insulation (2) *   02.19.2026    
-- -- Inspection (Insulation) (1)  02.19.2026    
-- -- Inspection (Electric Service) (0)  01.15.2026    
-- -- Set Electric Meter (0) *   04.06.2026    
-- -- Inspection (Main Sewer Line) (0)  06.11.2026    
-- -- Inspection (Main Water Line) (0)  04.14.2026    
-- -- Order Interior Doors & Trim (0)  03.30.2026    
-- -- Drywall (Hang) (4) *   03.08.2026     in process 2/28
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   03.16.2026     In process 3/7
-- -- Paint 1 (1)  03.16.2026    
-- -- Garage Door (0)  09.25.2025    
-- -- House Numbers (0)  05.27.2026    
-- -- Mailbox (0)  06.04.2026    
-- -- Cabinet Installation (2) *   04.04.2026     Wed, Apr 1
-- -- Granite Installation (1) *   05.27.2026     May 15
-- -- Interior Trim - Install (3) *   04.09.2026    
-- -- Order Plumbing / Lighting Fixtures (0)  04.09.2026    
-- -- Interior Trim - Paint (1)  04.16.2026    
-- -- Luxury Vinyl Plank (3) *   04.27.2026     in process 4/22
-- -- Luxury Vinyl Tile (0)  04.27.2026    
-- -- Paint 2 (3)  05.13.2026    
-- -- Cover Floors (0)  05.27.2026    
-- -- Deliver Plumbing / Lighting Fixtures (0)  05.07.2026    
-- -- Shoe Moulding (0)  05.09.2026    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   05.21.2026    
-- -- Install Coded Lockbox (add extra keys) (0)  06.04.2026    
-- -- Pay Water / Sewer Taps (0)  06.11.2026    
-- -- Set Water Meter (1) *   06.15.2026    
-- -- Electric Trim Out (3) *   05.21.2026     in process 5/16
-- -- Ceiling Fans (0)  05.21.2026    
-- -- HVAC Trim Out (1) *   05.14.2026    
-- -- Blower Door Test (1)  06.25.2026    
-- -- Plumbing Trim Out (2) *   06.04.2026     Just needs kitchen faucet 5/2
-- -- Install Appliances (0) *   06.25.2026    
-- -- Paint 3 (2) *   06.25.2026     Pretty large blemish on the bathroom wall, but other than that appears to be completed
-- -- Carpet (2)  05.18.2026    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- Inspection (Final HVAC) (0)  06.25.2026    
-- -- Inspection (Final Plumbing) (0)  06.25.2026    
-- -- Inspection (Final Electric) (0)  06.25.2026    
-- -- Pre Walk Through (0)  06.25.2026    
-- -- Stain Hardwood Stairs (1) *   06.04.2026    
-- -- Cleaning (1)  06.29.2026    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Keys to Settlement Agent (0)  06.25.2026    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025    
-- -- Request Trash Tote From POA Manager (0)  06.25.2026    
-- -- Closing (1)  06.25.2026    
-- -- Remove Coded Lockbox (0)  06.25.2026