- 14  ::  1685 Bald Eagle Circle
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Wed    Nov 27      Ratified Contract? (0)      
Wed    Nov 27      $2500 Deposit Received (0)      
Wed    Nov 27      Association Packet Requested (0)      
Wed    Nov 27      Association Packet Received (0)      
Wed    Nov 27      Selections Meeting (0)      
Wed    Nov 27      Selections Sheet Signed (0)      
Wed    Nov 27      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Wed    Nov 27      Deposit For Upgrades Received (0)      
Wed    Nov 27      Inspection (Concrete Wall) (1)      
Thu    Nov 28      Inspection (Conduit Under Slab) (1)      
Fri    Nov 29      Inspection (Drain Tile) (0)      
Fri    Nov 29      Settlement Agent Confirmed (0)      
Fri    Nov 29      Verify Window & Roof Structure (0)      
Fri    Nov 29      Order Appliances (0)      
Fri    Nov 29      Patio (0)      
Fri    Nov 29      Rough In Microwave Vent (0)      
Fri    Nov 29      Inspection (Rough In Plumbing) (1)      
Mon    Dec 2      Inspection (Rough In Electric) (1)      
Tue    Dec 3      Inspection (Deck Piers) (0)      
Tue    Dec 3      Inspection (Framing) (1)      
Wed    Dec 4      Exterior Stone (0)      
Wed    Dec 4      Set Electric Meter (0)      
Wed    Dec 4      Inspection (Main Water Line) (0)      
Wed    Dec 4      Loan Approval (0)      
Wed    Dec 4      Deed Preparation (0)      
Wed    Dec 4      Mailbox (0)      
Wed    Dec 4      Order Plumbing / Lighting Fixtures (0)      
Wed    Dec 4      Interior Trim - Paint (1)      
Thu    Dec 5      Ceiling Fans (0)      
Thu    Dec 5      Blower Door Test (1)      
Fri    Dec 6      Inspection (Final HVAC) (1)      
Mon    Dec 9      Inspection (Final Plumbing) (1)      
Tue    Dec 10      Inspection (Final Electric) (1)      
Wed    Dec 11      Stain Hardwood Stairs (1)      
Thu    Dec 12      Schedule Closing (0)      
Thu    Dec 12      Keys to Settlement Agent (0)      
Thu    Dec 12      Review Settlement Statement (0)      
Thu    Dec 12      Jerry Signs Closing Documents (0)      
Thu    Dec 12      Request Trash Tote From POA Manager (0)      
Thu    Dec 12      Remove Coded Lockbox (0)      
--   --   Install the last few windows and doors;
--   --   Plumb gas line for stove
--   --   Plumb gas line for fireplace
--   --   Darker Shutters EXACTLY LIKE LOT 32
--   --   No hardwood in alcoves by front door. See note in changes. Please change as soon as possible
--   --   Deck Rail and Steps
--   --   Please cover granite!!! K: 7/25: cover island please
--   --   Basement bath closet flooring? Ceramic tile
--   --   Buyer wants mulch NOT rock
--   --   Drywall arhes
--   --   Drywall arches
--   --   Deck
--   --   Hardwood laminate at the bottom of the steps
--   --   Living room floor vent cut wider
--   --   Bottom trim on shelf at arches?
--   --   Touch up grout in several placesn master bath
--   --   Touch up paint
--   --   Fix baseboard in master linen closet
--   --   Finish trim/ shoe old in downstairs bath closet
--   --   Touch up paint
--   --   Touch up cleaning
--   --   Poly steps and paint risers
--   --   Touch up grout in master bath
--   --   One window on the side of the house is missing shutters Tom
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       4/11: Setting roof trusses;
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       Remainder will arrive May 10;
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)       Shingles going on now;
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       In process
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday, May 17
-- -- Plumbing Rough In (4)       Plumbing gas line;
-- -- Electric Rough In (4)       Nearly done;
-- -- Exterior Vinyl (0) *        K: 6/20 nearly complete
-- -- Insulation (2)       Wednesday, May 18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Meter base to be set May 16
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        K: in process
-- -- Paint 1 (1)       Primed on June 10;
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery June 16; Install June 20;
-- -- Granite Installation (1) *        July 5
-- -- Interior Trim - Install (3)       K: 6/20 nearly complete
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       7/25 K: Everything complete except shower
-- -- Paint 2 (3)       7/25: K: finishing 7/27
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       July 25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       8/1 almost complete
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Friday, July 29
-- -- Install Appliances (0) *        July 25
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Mon, Aug 1
-- -- Pre Walk Through (0)       Mon, Aug 1
-- -- Cleaning (1)       July 30 (Cheryl)
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       8/3 at 11:00
-- -- Payment for Upgrades (0)      
-- -- Closing (1)