- 14  ::  1685 Bald Eagle Circle
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Order Appliances (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Order Plumbing / Lighting Fixtures (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Schedule Closing (0)      
Tue    Dec 30      Keys to Settlement Agent (0)      
Tue    Dec 30      Review Settlement Statement (0)      
Tue    Dec 30      Jerry Signs Closing Documents (0)      
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
Tue    Dec 30      Remove Coded Lockbox (0)      
--   --   Install the last few windows and doors;
--   --   Plumb gas line for stove
--   --   Plumb gas line for fireplace
--   --   Darker Shutters EXACTLY LIKE LOT 32
--   --   No hardwood in alcoves by front door. See note in changes. Please change as soon as possible
--   --   Deck Rail and Steps
--   --   Please cover granite!!! K: 7/25: cover island please
--   --   Basement bath closet flooring? Ceramic tile
--   --   Buyer wants mulch NOT rock
--   --   Drywall arhes
--   --   Drywall arches
--   --   Deck
--   --   Hardwood laminate at the bottom of the steps
--   --   Living room floor vent cut wider
--   --   Bottom trim on shelf at arches?
--   --   Touch up grout in several placesn master bath
--   --   Touch up paint
--   --   Fix baseboard in master linen closet
--   --   Finish trim/ shoe old in downstairs bath closet
--   --   Touch up paint
--   --   Touch up cleaning
--   --   Poly steps and paint risers
--   --   Touch up grout in master bath
--   --   One window on the side of the house is missing shutters Tom
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       4/11: Setting roof trusses;
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        Remainder will arrive May 10;
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        Shingles going on now;
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        In process
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       Plumbing gas line;
-- -- Electric Rough In (4)       Nearly done;
-- -- Inspection (Rough In HVAC) (1)       Tuesday, May 17
-- -- Exterior Vinyl (0) *        K: 6/20 nearly complete
-- -- Insulation (2) *        Wednesday, May 18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Meter base to be set May 16
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        K: in process
-- -- Paint 1 (1)       Primed on June 10;
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery June 16; Install June 20;
-- -- Granite Installation (1) *        July 5
-- -- Interior Trim - Install (3) *        K: 6/20 nearly complete
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       7/25 K: Everything complete except shower
-- -- Paint 2 (3)       7/25: K: finishing 7/27
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        July 25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        8/1 almost complete
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Friday, July 29
-- -- Install Appliances (0) *        July 25
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Mon, Aug 1
-- -- Pre Walk Through (0)       Mon, Aug 1
-- -- Cleaning (1)       July 30 (Cheryl)
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        8/3 at 11:00
-- -- Payment for Upgrades (0)      
-- -- Closing (1)