Wed |
Nov 27 |
Ratified Contract? (0) |
|
|
Wed |
Nov 27 |
$2500 Deposit Received (0) |
|
|
Wed |
Nov 27 |
Association Packet Requested (0) |
|
|
Wed |
Nov 27 |
Association Packet Received (0) |
|
|
Wed |
Nov 27 |
Selections Meeting (0) |
|
|
Wed |
Nov 27 |
Selections Sheet Signed (0) |
|
|
Wed |
Nov 27 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Wed |
Nov 27 |
Deposit For Upgrades Received (0) |
|
|
Wed |
Nov 27 |
Inspection (Concrete Wall) (1) |
|
|
Thu |
Nov 28 |
Inspection (Conduit Under Slab) (1) |
|
|
Fri |
Nov 29 |
Inspection (Drain Tile) (0) |
|
|
Fri |
Nov 29 |
Settlement Agent Confirmed (0) |
|
|
Fri |
Nov 29 |
Verify Window & Roof Structure (0) |
|
|
Fri |
Nov 29 |
Patio (0) |
|
|
Fri |
Nov 29 |
Rough In Microwave Vent (0) |
|
|
Fri |
Nov 29 |
Inspection (Rough In Plumbing) (1) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Electric) (1) |
|
|
Tue |
Dec 3 |
Inspection (Deck Piers) (0) |
|
|
Tue |
Dec 3 |
Inspection (Framing) (1) |
|
|
Wed |
Dec 4 |
Exterior Stone (0) |
|
|
Wed |
Dec 4 |
Set Electric Meter (0) |
|
|
Wed |
Dec 4 |
Inspection (Main Water Line) (0) |
|
|
Wed |
Dec 4 |
Loan Approval (0) |
|
|
Wed |
Dec 4 |
Deed Preparation (0) |
|
|
Wed |
Dec 4 |
Mailbox (0) |
|
|
Wed |
Dec 4 |
Interior Trim - Paint (1) |
|
|
Thu |
Dec 5 |
Ceiling Fans (0) |
|
|
Thu |
Dec 5 |
Blower Door Test (1) |
|
|
Fri |
Dec 6 |
Inspection (Final HVAC) (1) |
|
|
Mon |
Dec 9 |
Inspection (Final Plumbing) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Electric) (1) |
|
|
Wed |
Dec 11 |
Stain Hardwood Stairs (1) |
|
|
Thu |
Dec 12 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
On Site Meeting Wed, Sep 25 @ 4PM; |
|
|
-- |
-- |
Window in basement crooked? |
|
|
-- |
-- |
BUYERS EAGER TO CLOSE BY 1/20 |
|
|
-- |
-- |
Buyers want to seal garage floor and all unfinished concrete before closing- doable? cost? |
Tom |
|
-- |
-- |
Do not need toilet paper holders installed in any bathroom |
Kate to communicate with Ron |
|
-- |
-- |
ring towel holders at all bathroom sinks |
|
|
-- |
-- |
Hooks instead of rods |
|
|
-- |
-- |
Kate to schedule meetign with Ron for placement of all bath accessories |
|
|
-- |
-- |
Please add hand held to shower head for Martins- |
Kate to get options from Ferguson |
|
-- |
-- |
Buyer would like diagonal bar in shower |
|
|
-- |
-- |
Second Floor Drain |
|
|
-- |
-- |
2 lights by front door/2 on garage fyi for ordering 11/23 |
see additional pic 12/1 |
|
-- |
-- |
Expanded patio off basement? |
|
|
-- |
-- |
Trim Out |
Isaac |
|
-- |
-- |
FENCO- cultured marble tops to include an added up hall bath at 31" |
|
|
-- |
-- |
Pratt and Lambert - shell white |
|
|
-- |
-- |
Would like to increase concrete pad |
Tom & Kate working on it 1/2 |
|
-- |
-- |
Tile in basement bath covered but not grouted 1/5 |
|
|
-- |
-- |
Floor into office cracks/pops loudly 1/8 |
Tom |
|
-- |
-- |
|
|
|
-- |
-- |
Cabinet hardware |
Jan 9 |
|
-- |
-- |
Keep Derik Trissel updated on timing |
|
|
-- |
-- |
Garage door molding 1/11 |
|
|
-- |
-- |
Molding on kitchen cabinets 1/22 |
Red knows 2/5 |
|
-- |
-- |
Silt fence needs repairs in a few sections 1/11 |
|
|
-- |
-- |
Confirm mailbox will not be crooked 1/15 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Cultured marble |
Master bath - Thu, Jan 23 |
|
-- |
-- |
Few missing pieces cabinet molding 1/19 |
|
|
-- |
-- |
Staining of steps only 1/2 completed 1/19? |
|
|
-- |
-- |
CODED LOCKBOX 4040 |
|
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
Attic cover needed in garage 1/26 |
|
|
-- |
-- |
Aiming to close on February 11 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Fire extinguisher? |
|
|
-- |
-- |
Dents in wood near fridge 2/1 |
Tom |
|
-- |
-- |
Paint 3 is not done 2/1 |
Isaac |
|
-- |
-- |
Cabinet door needs installed sitting in kitchen 2/1 |
Red |
|
-- |
-- |
Kit island molding needed 2/1 |
Red - in process 2/5 |
|
-- |
-- |
MB light fixture crooked 2/1 |
Looks better-2/8 |
|
-- |
-- |
|
|
|
-- |
-- |
Shutters |
|
|
-- |
-- |
Cabinet hardware in laundry room |
|
|
-- |
-- |
Red needs 3 pulls for cabinets in MB |
Get Monday from Classic Kitchens |
|
-- |
-- |
End of driveway repairs 2/5 |
Spring |
|
-- |
-- |
Ceiling touch up basement room 2/5 |
ISAAC |
|
-- |
-- |
|
|
|
-- |
-- |
tighten hinges on cabinets in kitchen next to laundry door and cabinet in master bathroom |
RED-I think completed 2/8 |
|
-- |
-- |
fix stair issue- needs poly |
ISSAC |
|
-- |
-- |
Red to hang curtain rods |
RED |
|
-- |
-- |
loose damaged gusset bottom of attic truss- per reccomendations |
RED |
|
-- |
-- |
Have heat pump examined by Excel |
EXCEL |
|
-- |
-- |
Fix insulation in attic |
GREG |
|
-- |
-- |
Floor drain in basement to be uncovered |
RED |
|
-- |
-- |
Fix insulation in basement |
GREG |
|
-- |
-- |
fasteners to be added to deck railing at rear and at decking board at outside edge |
RED |
|
-- |
-- |
Lightbulb needed downstairs bathroom vanity light |
|
|
-- |
-- |
Power wash concrete patio |
|
|
-- |
-- |
Cut back rubber flashing |
|
|
-- |
-- |
Patch cement |
patio - Red or JB |
|
-- |
-- |
Silver blades need to be added to living room ceiling fan |
|
|
-- |
-- |
Stopper hinge on cabinet to the left of cabinet. |
Kate emailed Kimberly for hinges 2/7 - Red or JB |
|
-- |
-- |
Power wash deck |
|
|
-- |
-- |
Top drawer left of oven is crooked |
|
|
-- |
-- |
Far left island door needs replacement |
On site, waiting to install - Red or JB |
|
-- |
-- |
Right sink door needs replacement |
On site, waiting to install - Red or JB |
|
-- |
-- |
|
|
|
-- |
-- |
Exterior garage door key pad need a to be installed |
|
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
Repaint garage? Touch up paint throughout 2/8 |
|
|
-- |
-- |
Comcast needs to run a line |
|
|
-- |
-- |
Replace drawer front that was mis-drilled |
On site, waiting to install - Red or JB |
|
-- |
-- |
Replace garage door weather stripping |
Greg S |
|
-- |
-- |
Dan Martin = 540-820-5471 |
|
|
-- |
-- |
Install numbers on mailbox |
|
|
-- |
-- |
Red left a bucket with things in it at the house |
|
|
-- |
-- |
Cracked window frame |
11/16 - John Weeks to fix 12/5 (Saturday) |
|
-- |
-- |
Replace dead shrub |
|
|
-- |
-- |
Re-seed trouble spots in yard |
Tom told Roger about it |
|
-- |
-- |
Peeling paint on the garage |
Isaac |
|
-- |
-- |
Resurfacing of concrete patio |
Red |
|
-- |
-- |
Landscaping at back corner of the lot |
Pettit knows and will fix when they do other landscaping at HE29 |
|
-- |
-- |
Issues with concrete patio under deck |
Coating discolors when wet - Tom will call Scott at Superior |
|
-- |
-- |
Building Permit (30) |
Plans sent to printer on June 17 |
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
7/29 starting |
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
Alex |
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
Fri, Aug 30 |
|
-- |
-- |
Prepare Slab (1) |
Tues, Sep 3 |
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
Wed, Sep 4 |
|
-- |
-- |
Framing I (9) |
Starting Sep 9 |
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
90% done 10/30 |
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Order Appliances (0) |
|
|
-- |
-- |
Deck (0) |
being installed 1/8 |
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
To be formed on Fri, Jan 24 |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Mon, Nov 4 |
|
-- |
-- |
Plumbing Rough In (4) |
Plumbing inspection 10/30 |
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
Stone 95% complete 1/5 |
|
-- |
-- |
Insulation (2) |
Mon, Nov 4 |
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
Pipe is in |
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
In process 11/9 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
All taped/needs sanding 12/7 |
|
-- |
-- |
Paint 1 (1) |
Wed, Dec 11 |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Installing hardware 1/8 |
|
-- |
-- |
Granite Installation (1) * |
Thurs, Jan 16 |
|
-- |
-- |
Interior Trim - Install (3) |
Let MRTINS KNOW WHEN TRIM COMPLETE FOR WINDOW MEASUREMENTS/in process 12/28 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Just needs grout in shower 1/19 |
|
-- |
-- |
Paint 2 (3) |
|
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Shoe Moulding (0) |
Jan 23 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
In process 1/29 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Set Water Meter (0) |
Fri, Jan 24 |
|
-- |
-- |
Electric Trim Out (3) |
In process 1/15 |
|
-- |
-- |
HVAC Trim Out (1) |
Heat pump set 1/11 |
|
-- |
-- |
Plumbing Trim Out (2) |
In process 1/29 |
|
-- |
-- |
Install Appliances (0) * |
Wed, Jan 29 |
|
-- |
-- |
Paint 3 (2) * |
|
|
-- |
-- |
Carpet (2) |
Needed on second floor |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
Fri, Jan 31 or Mon, Feb 3 (reinspect Mon Feb 3) |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
Finish cleaning over weekend |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Friday at 9:30 |
|
-- |
-- |
Payment for Upgrades (0) |
$8,665 |
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
|
|
-- |
-- |
Closing (1) |
West View Title, Mon, Feb 10 at 10:00 AM |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|