3 32 16 14 15 39 1 24 5 30 29 17 10 40 4 27 7 22 ADDR
- 40  ::  1647 Bald Eagle Circle
[ BUILD: 1907-0001 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Wed    Nov 27      Ratified Contract? (0)      
Wed    Nov 27      $2500 Deposit Received (0)      
Wed    Nov 27      Association Packet Requested (0)      
Wed    Nov 27      Association Packet Received (0)      
Wed    Nov 27      Selections Meeting (0)      
Wed    Nov 27      Selections Sheet Signed (0)      
Wed    Nov 27      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Wed    Nov 27      Deposit For Upgrades Received (0)      
Wed    Nov 27      Inspection (Concrete Wall) (1)      
Thu    Nov 28      Inspection (Conduit Under Slab) (1)      
Fri    Nov 29      Inspection (Drain Tile) (0)      
Fri    Nov 29      Settlement Agent Confirmed (0)      
Fri    Nov 29      Verify Window & Roof Structure (0)      
Fri    Nov 29      Patio (0)      
Fri    Nov 29      Rough In Microwave Vent (0)      
Fri    Nov 29      Inspection (Rough In Plumbing) (1)      
Mon    Dec 2      Inspection (Rough In Electric) (1)      
Tue    Dec 3      Inspection (Deck Piers) (0)      
Tue    Dec 3      Inspection (Framing) (1)      
Wed    Dec 4      Exterior Stone (0)      
Wed    Dec 4      Set Electric Meter (0)      
Wed    Dec 4      Inspection (Main Water Line) (0)      
Wed    Dec 4      Loan Approval (0)      
Wed    Dec 4      Deed Preparation (0)      
Wed    Dec 4      Mailbox (0)      
Wed    Dec 4      Interior Trim - Paint (1)      
Thu    Dec 5      Ceiling Fans (0)      
Thu    Dec 5      Blower Door Test (1)      
Fri    Dec 6      Inspection (Final HVAC) (1)      
Mon    Dec 9      Inspection (Final Plumbing) (1)      
Tue    Dec 10      Inspection (Final Electric) (1)      
Wed    Dec 11      Stain Hardwood Stairs (1)      
Thu    Dec 12      Request Trash Tote From POA Manager (0)      
--   --   On Site Meeting Wed, Sep 25 @ 4PM;
--   --   Window in basement crooked?
--   --   BUYERS EAGER TO CLOSE BY 1/20
--   --   Buyers want to seal garage floor and all unfinished concrete before closing- doable? cost? Tom
--   --   Do not need toilet paper holders installed in any bathroom Kate to communicate with Ron
--   --   ring towel holders at all bathroom sinks
--   --   Hooks instead of rods
--   --   Kate to schedule meetign with Ron for placement of all bath accessories
--   --   Please add hand held to shower head for Martins- Kate to get options from Ferguson
--   --   Buyer would like diagonal bar in shower
--   --   Second Floor Drain
--   --   2 lights by front door/2 on garage fyi for ordering 11/23 see additional pic 12/1
--   --   Expanded patio off basement?
--   --   Trim Out Isaac
--   --   FENCO- cultured marble tops to include an added up hall bath at 31"
--   --   Pratt and Lambert - shell white
--   --   Would like to increase concrete pad Tom & Kate working on it 1/2
--   --   Tile in basement bath covered but not grouted 1/5
--   --   Floor into office cracks/pops loudly 1/8 Tom
--   --  
--   --   Cabinet hardware Jan 9
--   --   Keep Derik Trissel updated on timing
--   --   Garage door molding 1/11
--   --   Molding on kitchen cabinets 1/22 Red knows 2/5
--   --   Silt fence needs repairs in a few sections 1/11
--   --   Confirm mailbox will not be crooked 1/15
--   --  
--   --   Cultured marble Master bath - Thu, Jan 23
--   --   Few missing pieces cabinet molding 1/19
--   --   Staining of steps only 1/2 completed 1/19?
--   --   CODED LOCKBOX 4040
--   --  
--   --  
--   --  
--   --   Attic cover needed in garage 1/26
--   --   Aiming to close on February 11
--   --  
--   --   Fire extinguisher?
--   --   Dents in wood near fridge 2/1 Tom
--   --   Paint 3 is not done 2/1 Isaac
--   --   Cabinet door needs installed sitting in kitchen 2/1 Red
--   --   Kit island molding needed 2/1 Red - in process 2/5
--   --   MB light fixture crooked 2/1 Looks better-2/8
--   --  
--   --   Shutters
--   --   Cabinet hardware in laundry room
--   --   Red needs 3 pulls for cabinets in MB Get Monday from Classic Kitchens
--   --   End of driveway repairs 2/5 Spring
--   --   Ceiling touch up basement room 2/5 ISAAC
--   --  
--   --   tighten hinges on cabinets in kitchen next to laundry door and cabinet in master bathroom RED-I think completed 2/8
--   --   fix stair issue- needs poly ISSAC
--   --   Red to hang curtain rods RED
--   --   loose damaged gusset bottom of attic truss- per reccomendations RED
--   --   Have heat pump examined by Excel EXCEL
--   --   Fix insulation in attic GREG
--   --   Floor drain in basement to be uncovered RED
--   --   Fix insulation in basement GREG
--   --   fasteners to be added to deck railing at rear and at decking board at outside edge RED
--   --   Lightbulb needed downstairs bathroom vanity light
--   --   Power wash concrete patio
--   --   Cut back rubber flashing
--   --   Patch cement patio - Red or JB
--   --   Silver blades need to be added to living room ceiling fan
--   --   Stopper hinge on cabinet to the left of cabinet. Kate emailed Kimberly for hinges 2/7 - Red or JB
--   --   Power wash deck
--   --   Top drawer left of oven is crooked
--   --   Far left island door needs replacement On site, waiting to install - Red or JB
--   --   Right sink door needs replacement On site, waiting to install - Red or JB
--   --  
--   --   Exterior garage door key pad need a to be installed
--   --  
--   --  
--   --  
--   --   Repaint garage? Touch up paint throughout 2/8
--   --   Comcast needs to run a line
--   --   Replace drawer front that was mis-drilled On site, waiting to install - Red or JB
--   --   Replace garage door weather stripping Greg S
--   --   Dan Martin = 540-820-5471
--   --   Install numbers on mailbox
--   --   Red left a bucket with things in it at the house
--   --   Cracked window frame 11/16 - John Weeks to fix 12/5 (Saturday)
--   --   Replace dead shrub
--   --   Re-seed trouble spots in yard Tom told Roger about it
--   --   Peeling paint on the garage Isaac
--   --   Resurfacing of concrete patio Red
--   --   Landscaping at back corner of the lot Pettit knows and will fix when they do other landscaping at HE29
--   --   Issues with concrete patio under deck Coating discolors when wet - Tom will call Scott at Superior
-- -- Building Permit (30)       Plans sent to printer on June 17
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)       7/29 starting
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       Alex
-- -- Inspection (Plumbing Under Slab) (1)       Fri, Aug 30
-- -- Prepare Slab (1)       Tues, Sep 3
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Wed, Sep 4
-- -- Framing I (9)       Starting Sep 9
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)       90% done 10/30
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       being installed 1/8
-- -- Gutters (0)      
-- -- Driveway (0)       To be formed on Fri, Jan 24
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Mon, Nov 4
-- -- Plumbing Rough In (4)       Plumbing inspection 10/30
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *        Stone 95% complete 1/5
-- -- Insulation (2)       Mon, Nov 4
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Pipe is in
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 11/9
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        All taped/needs sanding 12/7
-- -- Paint 1 (1)       Wed, Dec 11
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Installing hardware 1/8
-- -- Granite Installation (1) *        Thurs, Jan 16
-- -- Interior Trim - Install (3)       Let MRTINS KNOW WHEN TRIM COMPLETE FOR WINDOW MEASUREMENTS/in process 12/28
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Just needs grout in shower 1/19
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       Jan 23
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process 1/29
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)       Fri, Jan 24
-- -- Electric Trim Out (3)       In process 1/15
-- -- HVAC Trim Out (1)       Heat pump set 1/11
-- -- Plumbing Trim Out (2)       In process 1/29
-- -- Install Appliances (0) *        Wed, Jan 29
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Needed on second floor
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Fri, Jan 31 or Mon, Feb 3 (reinspect Mon Feb 3)
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Finish cleaning over weekend
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Friday at 9:30
-- -- Payment for Upgrades (0)       $8,665
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title, Mon, Feb 10 at 10:00 AM
-- -- Remove Coded Lockbox (0)