3 32 16 14 15 39 1 24 5 30 29 17 10 40 4 27 7 22 ADDR
- 17  ::  1697 Bald Eagle Circle
[ BUILD: 2001-0138 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Marianne 540-383-9872
Wed    Nov 27      Ratified Contract? (0)      
Wed    Nov 27      $2500 Deposit Received (0)      
Wed    Nov 27      Association Packet Requested (0)      
Wed    Nov 27      Association Packet Received (0)      
Wed    Nov 27      Selections Meeting (0)      
Wed    Nov 27      Selections Sheet Signed (0)      
Wed    Nov 27      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Wed    Nov 27      Deposit For Upgrades Received (0)      
Wed    Nov 27      Building Permit (30)      
Wed    Jan 8      Inspection (Concrete Wall) (1)      
Thu    Jan 9      Inspection (Conduit Under Slab) (1)      
Fri    Jan 10      Inspection (Drain Tile) (0)      
Fri    Jan 10      Settlement Agent Confirmed (0)      
Fri    Jan 10      Verify Window & Roof Structure (0)      
Fri    Jan 10      Patio (0)      
Fri    Jan 10      Rough In Microwave Vent (0)      
Fri    Jan 10      Inspection (Rough In Plumbing) (1)      
Mon    Jan 13      Inspection (Rough In Electric) (1)      
Tue    Jan 14      Inspection (Deck Piers) (0)      
Tue    Jan 14      Inspection (Framing) (1)      
Wed    Jan 15      Exterior Stone (0)      
Wed    Jan 15      Set Electric Meter (0)      
Wed    Jan 15      Inspection (Main Water Line) (0)      
Wed    Jan 15      Loan Approval (0)      
Wed    Jan 15      Deed Preparation (0)      
Wed    Jan 15      Mailbox (0)      
Wed    Jan 15      Interior Trim - Paint (1)      
Thu    Jan 16      Ceiling Fans (0)      
Thu    Jan 16      Blower Door Test (1)      
Fri    Jan 17      Inspection (Final HVAC) (1)      
Mon    Jan 20      Inspection (Final Plumbing) (1)      
Tue    Jan 21      Inspection (Final Electric) (1)      
Wed    Jan 22      Stain Hardwood Stairs (1)      
Thu    Jan 23      Request Trash Tote From POA Manager (0)      
--   --   Check notes
--   --   Electrical notes- , Dimmer switch on dining light,
--   --   Electrical notes Porch fan and light- living room two elevated receptacles
--   --   Electrical notes- two exterior lights on deck,
--   --   Make sure fireplace has blower
--   --   Electrical notes Outlet over fireplace, ceiling fan centered with 8 snaps on either side
--   --   Electrical notes Two exterior lights on deck, electrical behind every toilet
--   --   Electrical notes Office- 4 snaps switched 2/2, Those basement bedrooms with switched receptacle
--   --   Want good wall cap for half wall going down steps
--   --   Wal through notes Blower on fireplace, added ceiling fans in both down bedrooms, and ceiling fan kit in basement LR
--   --   Electrical notes 4 snaps in basement FR balanced with fan, and four more on other side of drop ceiling
--   --   Walk through notes Basement bath cubby with wood shelves to be painted white
--   --   Walk through notes- Door swing change into linen closet in basement bathroom
--   --   rough-in venting radon to roof-cost?
--   --   Pull down
--   --   Pull down stairs in garage In process 6/17
--   --   Rough in vent to attic/roof
--   --   Laundry room pocket door 6/14
--   --   Pedestal sink 6/14
--   --   Two speaker framed out drywall boxes- header height and 16 inches tall Note taped inside for harry.
--   --   PAINT COLOR- BM color filtered sunshine- 2154-60, FRONT DOOR COLOR BM color HC- 182 Classic Burgundy Monday, October 5
--   --   STUCCO COLOR- Moonlit sand 10611. BRICK SURROUND ALL WINDOWS AND DOORS- Portsmouth brick
--   --   Cover steps
--   --   Outlet over fireplace 7/3 wires there. Harry just need to cut it out 9/17
--   --   Gas tank for fireplace and backup for furnace Monday, Sept 14-hole dug 9/13
--   --   (gas backup on furnace)
--   --   Must be in home by end of September!!!
--   --   Two missing half round windows Thu, Aug 27?
--   --  
--   --   Kitchen window needed 7/25
--   --   Richmond Mantle with black slate surround set to be installed Monday 10/5 GWB
--   --   Kitchen island does not exactly match plans online 8/23
--   --   Interior trim needed in basement 8/23
--   --   waiting on back splash decision
--   --   Raise kitchen window
--   --   Cost for concrete? To be discussed at OPS
--   --   NEED electrical upgrade list from Harry Greg to follow up
--   --   who is installing buyer provided shower door- CJ to install 9/28 with appliances
--   --   Check for D, E, F, G (court) Kitchen accessories 8/29 F,G 9/2
--   --   Trim on MB window Galindez to take care of it during final paint GWB
--   --   Bathroom cabinets-right before ceramics installed 9/9
--   --   Painted wood shelves for basement linen closet Tom to tell trim guy
--   --   Access panel under stairs for whirlpool
--   --   Add light in attic space above garage
--   --   Motion lights for laundry. Buyer provides???
--   --  
--   --   Trim out a few windows
--   --   Harry to finish trim out Thursday
--   --   Sink in basement bar needs to be attached Tom will ask owners about missing clips
--   --   Left nook shelf uneven
--   --   Left nook shelf uneven
--   --   Floor transition strip-sauna room to family room 9/23 Few missing throughout house
--   --   Short on ceramic in shower in basement bath 9/23 On site 10/7
--   --   Trim needed basement door 9/27 Isaac
--   --   Drain for water heater Hawkeye is working on it now. 10/1 GWB
--   --   CODED LOCKBOX 1717
--   --   Dimmable light bulbs needed 9/30 Emailed Greg size :)
--   --   Stain steps Needs poly 10/7
--   --   Paint attic cover Galindez to finish 10/5
--   --  
--   --   Few HVAC covers missing & thermostat
--   --   Paint touch up needed throughout Galindez to finish 10/5-needs touch up throughout 10/7
--   --   Electric trim out still in process 10/3
--   --   Discoloration in shower 10/7 Greg will follow up with Joe
--   --   Pantry-shelving? Drywall sanding? Kate checking
--   --   Trim around bar Greg will talk to Classic
--   --   Water filter hookup
--   --   Cracked master sink Repair
--   --   Fix small kitchen cabinet Russell
--   --   Sand and Paint trim on Kitchen window Galindez GWB
--   --   Paint touch up in basement bath around light switch Galindez GWB
--   --   Get pilot light started for fireplace Carlos to call Marianne 9/18 GWB
--   --   Living room ceiling fan/light not working Spoke with Harry - Its a fan/remote issue not an electrical problem
--   --   Missing trim on living room side door Galindez GWB
--   --   Wash fixed frame windows JB
--   --   Caulk/seal around furnace vent JB
--   --   Basement door not keyed to front door Ron
--   --   Repair sink in master bath Kevin Burton to repair week of 10/18
--   --   Credit for extra faucet? this shouldn t matter as they were never charged? GWB
--   --   Mailbox numbers JB
--   --   Appraisal and building spec for insurance
--   --   Touch up kit for cabinets Tom will drop off
--   --   Repair cracked sink or order new one? (Kate to contact Kara Marshall)
--   --   Repair or replace ceiling fan Fanamation (Kate to send model number to Jerry, Kara)
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Started 2/26
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       In process 4/29
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       In process 5/9
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       remainder arriving 6/17
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       Band board on outside of deck (we have the material now)
-- -- Gutters (0)       Mon, Oct 5
-- -- Driveway (0)       Patio needs poured 9/27
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 7/4
-- -- Inspection (Rough In HVAC) (1)       Just need mechanical and framing
-- -- Plumbing Rough In (4)       In process 6/17
-- -- Electric Rough In (4)       Harry has notes of changes
-- -- Exterior Vinyl (0) *        In process 9/16
-- -- Insulation (2)       Week of July 13
-- -- Inspection (Insulation) (1)       July 23
-- -- Inspection (Electric Service) (0)       Should happen 9/17
-- -- Inspection (Main Sewer Line) (0)       Paid should be set this week 9/16 GWB
-- -- Order Interior Doors & Trim (0)       On site 8/19
-- -- Drywall (Hang) (4) *        In process 8/1
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Just needs sanding 8/12
-- -- Paint 1 (1)       Starting today 8/17 GWB
-- -- Garage Door (0)       Door getting installed 8/18 GWB
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Sept 7-ish
-- -- Interior Trim - Install (3)       Galindez will finish 8/31 GWB-in process
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process 9/19-tile needs grout/shower in process
-- -- Paint 2 (3)       Galindez to start 9/2
-- -- Cover Floors (1)       Basement covered 9/19-up is not 9/27
-- -- Deliver Plumbing / Lighting Fixtures (0)       Set to deliver plumbing 8/26 GWB Owner providing lighting -pedestals and toilets on site 8/26
-- -- Shoe Moulding (0)       On site 9/7
-- -- Shelving, Door Knobs, Fire Extinguisher (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Monday, September 14
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process 9/30
-- -- HVAC Trim Out (1)       Furnace arrives Monday, install thereafter-started 10/3
-- -- Plumbing Trim Out (2)       In process 9/19
-- -- Install Appliances (0) *        Installed 9/29
-- -- Paint 3 (2) *        in process 9/30
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Monday, October 12
-- -- Pre Walk Through (0)       Monday 9/21 and Monday 9/28 GWB
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)      
-- -- Payment for Upgrades (0)       $56,459
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)