- 17  ::  1697 Bald Eagle Circle
[ BUILD: 2001-0138 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Marianne 540-383-9872
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Building Permit (30) *       
Mon    Jan 26      Inspection (Concrete Wall) (1)      
Tue    Jan 27      Inspection (Conduit Under Slab) (1)      
Wed    Jan 28      Inspection (Drain Tile) (0)      
Wed    Jan 28      Settlement Agent Confirmed (0)      
Wed    Jan 28      Verify Window & Roof Structure (0)      
Wed    Jan 28      Patio (0)      
Wed    Jan 28      Rough In Microwave Vent (0)      
Wed    Jan 28      Inspection (Rough In Plumbing) (1)      
Thu    Jan 29      Inspection (Rough In Electric) (1)      
Fri    Jan 30      Inspection (Framing) (1) *       
Mon    Feb 2      Inspection (Deck Piers) (0)      
Mon    Feb 2      Exterior Stone (0)      
Mon    Feb 2      Set Electric Meter (0) *       
Mon    Feb 2      Inspection (Main Water Line) (0)      
Mon    Feb 2      Loan Approval (0)      
Mon    Feb 2      Deed Preparation (0)      
Mon    Feb 2      Mailbox (0)      
Mon    Feb 2      Interior Trim - Paint (1)      
Tue    Feb 3      Ceiling Fans (0)      
Tue    Feb 3      Blower Door Test (1)      
Wed    Feb 4      Inspection (Final HVAC) (1)      
Thu    Feb 5      Inspection (Final Plumbing) (1)      
Fri    Feb 6      Inspection (Final Electric) (1)      
Mon    Feb 9      Stain Hardwood Stairs (1) *       
Tue    Feb 10      Request Trash Tote From POA Manager (0)      
--   --   Check notes
--   --   Electrical notes- , Dimmer switch on dining light,
--   --   Electrical notes Porch fan and light- living room two elevated receptacles
--   --   Electrical notes- two exterior lights on deck,
--   --   Make sure fireplace has blower
--   --   Electrical notes Outlet over fireplace, ceiling fan centered with 8 snaps on either side
--   --   Electrical notes Two exterior lights on deck, electrical behind every toilet
--   --   Electrical notes Office- 4 snaps switched 2/2, Those basement bedrooms with switched receptacle
--   --   Want good wall cap for half wall going down steps
--   --   Wal through notes Blower on fireplace, added ceiling fans in both down bedrooms, and ceiling fan kit in basement LR
--   --   Electrical notes 4 snaps in basement FR balanced with fan, and four more on other side of drop ceiling
--   --   Walk through notes Basement bath cubby with wood shelves to be painted white
--   --   Walk through notes- Door swing change into linen closet in basement bathroom
--   --   rough-in venting radon to roof-cost?
--   --   Pull down
--   --   Pull down stairs in garage In process 6/17
--   --   Rough in vent to attic/roof
--   --   Laundry room pocket door 6/14
--   --   Pedestal sink 6/14
--   --   Two speaker framed out drywall boxes- header height and 16 inches tall Note taped inside for harry.
--   --   PAINT COLOR- BM color filtered sunshine- 2154-60, FRONT DOOR COLOR BM color HC- 182 Classic Burgundy Monday, October 5
--   --   STUCCO COLOR- Moonlit sand 10611. BRICK SURROUND ALL WINDOWS AND DOORS- Portsmouth brick
--   --   Cover steps
--   --   Outlet over fireplace 7/3 wires there. Harry just need to cut it out 9/17
--   --   Gas tank for fireplace and backup for furnace Monday, Sept 14-hole dug 9/13
--   --   (gas backup on furnace)
--   --   Must be in home by end of September!!!
--   --   Two missing half round windows Thu, Aug 27?
--   --  
--   --   Kitchen window needed 7/25
--   --   Richmond Mantle with black slate surround set to be installed Monday 10/5 GWB
--   --   Kitchen island does not exactly match plans online 8/23
--   --   Interior trim needed in basement 8/23
--   --   waiting on back splash decision
--   --   Raise kitchen window
--   --   Cost for concrete? To be discussed at OPS
--   --   NEED electrical upgrade list from Harry Greg to follow up
--   --   who is installing buyer provided shower door- CJ to install 9/28 with appliances
--   --   Check for D, E, F, G (court) Kitchen accessories 8/29 F,G 9/2
--   --   Trim on MB window Galindez to take care of it during final paint GWB
--   --   Bathroom cabinets-right before ceramics installed 9/9
--   --   Painted wood shelves for basement linen closet Tom to tell trim guy
--   --   Access panel under stairs for whirlpool
--   --   Add light in attic space above garage
--   --   Motion lights for laundry. Buyer provides???
--   --  
--   --   Trim out a few windows
--   --   Harry to finish trim out Thursday
--   --   Sink in basement bar needs to be attached Tom will ask owners about missing clips
--   --   Left nook shelf uneven
--   --   Left nook shelf uneven
--   --   Floor transition strip-sauna room to family room 9/23 Few missing throughout house
--   --   Short on ceramic in shower in basement bath 9/23 On site 10/7
--   --   Trim needed basement door 9/27 Isaac
--   --   Drain for water heater Hawkeye is working on it now. 10/1 GWB
--   --   CODED LOCKBOX 1717
--   --   Dimmable light bulbs needed 9/30 Emailed Greg size :)
--   --   Stain steps Needs poly 10/7
--   --   Paint attic cover Galindez to finish 10/5
--   --  
--   --   Few HVAC covers missing & thermostat
--   --   Paint touch up needed throughout Galindez to finish 10/5-needs touch up throughout 10/7
--   --   Electric trim out still in process 10/3
--   --   Discoloration in shower 10/7 Greg will follow up with Joe
--   --   Pantry-shelving? Drywall sanding? Kate checking
--   --   Trim around bar Greg will talk to Classic
--   --   Water filter hookup
--   --   Cracked master sink Repair
--   --   Fix small kitchen cabinet Russell
--   --   Sand and Paint trim on Kitchen window Galindez GWB
--   --   Paint touch up in basement bath around light switch Galindez GWB
--   --   Get pilot light started for fireplace Carlos to call Marianne 9/18 GWB
--   --   Living room ceiling fan/light not working Spoke with Harry - Its a fan/remote issue not an electrical problem
--   --   Missing trim on living room side door Galindez GWB
--   --   Wash fixed frame windows JB
--   --   Caulk/seal around furnace vent JB
--   --   Basement door not keyed to front door Ron
--   --   Repair sink in master bath Kevin Burton to repair week of 10/18
--   --   Credit for extra faucet? this shouldn t matter as they were never charged? GWB
--   --   Mailbox numbers JB
--   --   Appraisal and building spec for insurance
--   --   Touch up kit for cabinets Tom will drop off
--   --   Repair cracked sink or order new one? (Kate to contact Kara Marshall)
--   --   Repair or replace ceiling fan Fanamation (Kate to send model number to Jerry, Kara)
-- -- Order Roof & Floor Trusses (1)      
    Concrete to be poured in the entire L shape under the Screened in porch and deck  
    Kitchen cabinets, hardware accessories, delivery and installation = $16,750 ($12000 allowance)  
    Rough in vent attic/roof future radon  
    Total cost of electrical upgrades  
    Recessed shelves in master closet  
    Building Speaker Cubbies-  
    Gas- Power Vent Gas Water Heater with venting through basement wall-  
    Brick window and door accents  
    Plumbing Upgrades from Shanks  
    Granite level 3- Salinas White  
    Credit for unused portion of $4800 allowance for basement vanities and toilets (cost of bathroom pantry plus one toilet = $2,450)  
    Washer and Dryer and install  
    Virginia Installations- upgrades includes added shelving, labor to install buyer provided wood shelving in several locations, upgraded keyless locks, also applies credits for buyer provided mirrors- price may increase if hourly labor increases  
    Appliances Bosch Kitchen upgrade with install  
    CREDIT- standard appliance package  
    CREDIT- buyer provided lighting  
    Install Cost for buyer provided Shower Door  
    Tile Labor upgrade over standard locations including niches spa tub wrap, wall tile kitchen backsplash  
    Walk In Shower Labor- (reduced by $1600 contract allowance)  
    Overage for using LVT over standard carpet standard, 2 upstairs bedrooms and all downstairs- Install included  
    Overage for Ceramic on walls and in showers and decos and extra setting materials.  
    Pantry Framing Changes  
    Staining, sanding and poly for steps  
    LP Furnace, burying tank, sand, piping  
    Octagon Window Upstairs  
    Plumbing Upgrades Dry River- 12 additional hours of work over standard  
    Base for sculpture  
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Started 2/26
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       In process 4/29
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       In process 5/9
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        remainder arriving 6/17
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       Band board on outside of deck (we have the material now)
-- -- Gutters (0)       Mon, Oct 5
-- -- Driveway (0) *        Patio needs poured 9/27
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 7/4
-- -- Plumbing Rough In (4)       In process 6/17
-- -- Electric Rough In (4)       Harry has notes of changes
-- -- Inspection (Rough In HVAC) (1)       Just need mechanical and framing
-- -- Exterior Vinyl (0) *        In process 9/16
-- -- Insulation (2) *        Week of July 13
-- -- Inspection (Insulation) (1)       July 23
-- -- Inspection (Electric Service) (0)       Should happen 9/17
-- -- Inspection (Main Sewer Line) (0)       Paid should be set this week 9/16 GWB
-- -- Order Interior Doors & Trim (0)       On site 8/19
-- -- Drywall (Hang) (4) *        In process 8/1
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Just needs sanding 8/12
-- -- Paint 1 (1)       Starting today 8/17 GWB
-- -- Garage Door (0)       Door getting installed 8/18 GWB
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Sept 7-ish
-- -- Interior Trim - Install (3) *        Galindez will finish 8/31 GWB-in process
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process 9/19-tile needs grout/shower in process
-- -- Paint 2 (3)       Galindez to start 9/2
-- -- Cover Floors (1)       Basement covered 9/19-up is not 9/27
-- -- Deliver Plumbing / Lighting Fixtures (0)       Set to deliver plumbing 8/26 GWB Owner providing lighting -pedestals and toilets on site 8/26
-- -- Shoe Moulding (0)       On site 9/7
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Monday, September 14
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        In process 9/30
-- -- HVAC Trim Out (1) *        Furnace arrives Monday, install thereafter-started 10/3
-- -- Plumbing Trim Out (2) *        In process 9/19
-- -- Install Appliances (0) *        Installed 9/29
-- -- Paint 3 (2) *        in process 9/30
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Monday, October 12
-- -- Pre Walk Through (0)       Monday 9/21 and Monday 9/28 GWB
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *       
-- -- Payment for Upgrades (0)       $56,459
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)