Refrigerator door replacement |
After Closing |
|
Wed |
Nov 27 |
Ratified Contract? (0) |
|
|
Wed |
Nov 27 |
$2500 Deposit Received (0) |
|
|
Wed |
Nov 27 |
Association Packet Requested (0) |
|
|
Wed |
Nov 27 |
Association Packet Received (0) |
|
|
Wed |
Nov 27 |
Selections Meeting (0) |
|
|
Wed |
Nov 27 |
Selections Sheet Signed (0) |
|
|
Wed |
Nov 27 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Wed |
Nov 27 |
Deposit For Upgrades Received (0) |
|
|
Wed |
Nov 27 |
Inspection (Concrete Wall) (1) |
|
|
Thu |
Nov 28 |
Inspection (Conduit Under Slab) (1) |
|
|
Fri |
Nov 29 |
Inspection (Drain Tile) (0) |
|
|
Fri |
Nov 29 |
Settlement Agent Confirmed (0) |
|
|
Fri |
Nov 29 |
Order Tubs / Showers (0) |
|
|
Fri |
Nov 29 |
Verify Window & Roof Structure (0) |
|
|
Fri |
Nov 29 |
Install Stairs (0) |
|
|
Fri |
Nov 29 |
House Number and Status in Window (0) |
|
|
Fri |
Nov 29 |
Order Appliances (0) |
|
|
Fri |
Nov 29 |
Patio (0) |
|
|
Fri |
Nov 29 |
Rough In Microwave Vent (0) |
|
|
Fri |
Nov 29 |
Inspection (Rough In Plumbing) (1) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Electric) (1) |
|
|
Tue |
Dec 3 |
Inspection (Deck Piers) (0) |
|
|
Tue |
Dec 3 |
Inspection (Framing) (1) |
|
|
Wed |
Dec 4 |
Exterior Stone (0) |
|
|
Wed |
Dec 4 |
Set Electric Meter (0) |
|
|
Wed |
Dec 4 |
Inspection (Main Water Line) (0) |
|
|
Wed |
Dec 4 |
Loan Approval (0) |
|
|
Wed |
Dec 4 |
Deed Preparation (0) |
|
|
Wed |
Dec 4 |
Garage Door (0) |
|
|
Wed |
Dec 4 |
Mailbox (0) |
|
|
Wed |
Dec 4 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Wed |
Dec 4 |
Interior Trim - Paint (1) |
|
|
Thu |
Dec 5 |
Cover Floors (1) |
|
|
Fri |
Dec 6 |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
Fri |
Dec 6 |
Shoe Moulding (0) |
|
|
Fri |
Dec 6 |
Set Water Meter (0) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Paint 3 (2) * |
|
|
Wed |
Dec 11 |
Appraiser Confirms Construction Completion (0) |
|
|
Wed |
Dec 11 |
Inspection (Final HVAC) (1) |
|
|
Thu |
Dec 12 |
Inspection (Final Plumbing) (1) |
|
|
Fri |
Dec 13 |
Inspection (Final Electric) (1) |
|
|
Mon |
Dec 16 |
Stain Hardwood Stairs (1) |
|
|
Tue |
Dec 17 |
C.O. to Lender (0) |
|
|
Tue |
Dec 17 |
Schedule Closing (0) |
|
|
Tue |
Dec 17 |
Payment for Upgrades (0) |
|
|
Tue |
Dec 17 |
Keys to Settlement Agent (0) |
|
|
Tue |
Dec 17 |
Review Settlement Statement (0) |
|
|
Tue |
Dec 17 |
Jerry Signs Closing Documents (0) |
|
|
Tue |
Dec 17 |
Request Trash Tote From POA Manager (0) |
|
|
Tue |
Dec 17 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Replace front of freezer (ding) |
Kate to call back service center with serial number |
|
-- |
-- |
Resolve basement shower issue |
|
|
-- |
-- |
When will we install ceramic back splash buyer would like to be present |
Needs thinset |
|
-- |
-- |
Butler's pantry |
Del Jan 23, Install Jan 24-26 |
|
-- |
-- |
Basement vanity |
Timing TBD |
|
-- |
-- |
Light fixture outside sliding door on main level |
|
|
-- |
-- |
Install shower door |
After Closing |
|
-- |
-- |
Remove granite backsplash |
|
|
-- |
-- |
Install ceramic tile backsplash |
February 3rd |
|
-- |
-- |
Install cedar siding in closet |
Tom to call- Mitch install Saturday |
|
-- |
-- |
Touch up ceiling paint very splotchy |
Thursday, Feb 16 |
|
-- |
-- |
Downstairs Shower? |
1/26 late in day |
|
-- |
-- |
Vinyl |
Tues, Feb 7 |
|
-- |
-- |
Backing in shower- tom to install grab bar, or Ron? |
Brushed nickel- get Ron to do |
|
-- |
-- |
Hardwood flooring issues upstairs |
|
|
-- |
-- |
Remove master closet shelving |
|
|
-- |
-- |
Install hardware on screen door |
JB |
|
-- |
-- |
Keypad at garage door |
Greg |
|
-- |
-- |
Install pull down stairs in garage |
|
|
-- |
-- |
Install light above butler's pantry |
|
|
-- |
-- |
Install missing under cabinet light under cabinet to left of refrigerator |
|
|
-- |
-- |
Under cabinet light in Butler cabinet |
|
|
-- |
-- |
TOM- PLEASE COVER RANGE TO PROTECT FROM TILE BACK SPLASH |
|
|
-- |
-- |
Install grab bar (VA Installation) |
Ron |
|
-- |
-- |
Mitch change out bathroom doors 2'6- put up oak handrail |
Change order fees. |
|
-- |
-- |
Ceramic back splash |
|
|
-- |
-- |
Fireplace in basement? |
|
|
-- |
-- |
Anchor bolt in storage room wall |
JB |
|
-- |
-- |
Thresholds at carpet- bedroom and office |
|
|
-- |
-- |
LED lights purchased by Tom |
|
|
-- |
-- |
Adding snap light over ceiling |
Added recently |
|
-- |
-- |
LED lights in master bathroom? |
|
|
-- |
-- |
Install and stain oak handrail |
Stained, just install |
|
-- |
-- |
Install keypad for garage door |
Greg |
|
-- |
-- |
Cleaning |
Cheryl |
|
-- |
-- |
Basement tub repair |
Friday, Feb 17 |
|
-- |
-- |
Stone and caulk repairs |
Friday, Feb 17 |
|
-- |
-- |
Mailbox repair |
Thursday, Feb 16 |
|
-- |
-- |
Replace kitchen cabinet fronts |
|
|
-- |
-- |
Replace damaged kitchen cabinet fronts |
|
|
-- |
-- |
HVAC cleaning |
TBD game plan |
|
-- |
-- |
Air handler cleaning |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
Materials have been ordered; |
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Tuesday morning 1/17 |
|
-- |
-- |
Plumbing Rough In (4) |
|
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
Tuesday morning 1/17 |
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
Tuesday afternoon 1/17 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
In process- complete by Monday afternoon the 23rd |
|
-- |
-- |
Paint 1 (1) |
Tuesday 1/24 |
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Del- Wed 2/1; Install Thursday the 2nd; Granite install 2/6 |
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
Mitch, Wed 1/25- through Friday 1/27 |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
|
|
-- |
-- |
Paint 2 (3) |
Saturday 28th and Sunday 29th |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Needs to be finished |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
Now |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
|
|
-- |
-- |
Install Appliances (0) * |
|
|
-- |
-- |
Carpet (2) |
Carpet and Vinyl- Friday the 3rd |
|
-- |
-- |
Inspection (Final Building) (2) * |
Tues, Feb 7 |
|
-- |
-- |
Pre Walk Through (0) |
Tuesday 2/7 |
|
-- |
-- |
Cleaning (1) |
Wed, Feb 8 - start upstairs |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
Buyer Walk Through (1) |
|
|
-- |
-- |
Closing (1) |
|
|