Wed |
Nov 27 |
Ratified Contract? (0) |
|
|
Wed |
Nov 27 |
$2500 Deposit Received (0) |
|
|
Wed |
Nov 27 |
Association Packet Requested (0) |
|
|
Wed |
Nov 27 |
Association Packet Received (0) |
|
|
Wed |
Nov 27 |
Selections Meeting (0) |
|
|
Wed |
Nov 27 |
Selections Sheet Signed (0) |
|
|
Wed |
Nov 27 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Wed |
Nov 27 |
Deposit For Upgrades Received (0) |
|
|
Wed |
Nov 27 |
Inspection (Concrete Wall) (1) |
|
|
Thu |
Nov 28 |
Inspection (Conduit Under Slab) (1) |
|
|
Fri |
Nov 29 |
Inspection (Drain Tile) (0) |
|
|
Fri |
Nov 29 |
Settlement Agent Confirmed (0) |
|
|
Fri |
Nov 29 |
Verify Window & Roof Structure (0) |
|
|
Fri |
Nov 29 |
Patio (0) |
|
|
Fri |
Nov 29 |
Rough In Microwave Vent (0) |
|
|
Fri |
Nov 29 |
Inspection (Rough In Plumbing) (1) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Electric) (1) |
|
|
Tue |
Dec 3 |
Inspection (Deck Piers) (0) |
|
|
Tue |
Dec 3 |
Inspection (Framing) (1) |
|
|
Wed |
Dec 4 |
Exterior Stone (0) |
|
|
Wed |
Dec 4 |
Set Electric Meter (0) |
|
|
Wed |
Dec 4 |
Inspection (Main Water Line) (0) |
|
|
Wed |
Dec 4 |
Loan Approval (0) |
|
|
Wed |
Dec 4 |
Deed Preparation (0) |
|
|
Wed |
Dec 4 |
Mailbox (0) |
|
|
Wed |
Dec 4 |
Interior Trim - Paint (1) |
|
|
Thu |
Dec 5 |
Ceiling Fans (0) |
|
|
Thu |
Dec 5 |
Blower Door Test (1) |
|
|
Fri |
Dec 6 |
Inspection (Final HVAC) (1) |
|
|
Mon |
Dec 9 |
Inspection (Final Plumbing) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Electric) (1) |
|
|
Wed |
Dec 11 |
Stain Hardwood Stairs (1) |
|
|
|
-- |
-- |
UPDATE CURTIS WITH ESTIMATED COMPLETION DATE |
|
|
-- |
-- |
SEND CURTIS ESTIMATED COMPLETION DATE |
|
|
-- |
-- |
Five pane kitchen window centered over kitchen sink |
(Per email from Curtis) - not per contract |
|
-- |
-- |
Deposit of $6,057 received March 25, 2020 |
|
|
-- |
-- |
Smooth sand appearance stucco |
Color to match 1677 Bald Eagle Circle |
|
-- |
-- |
Decorative vent accents in all peaks |
(such as on end of garage at 1677 Bald Eagle Circle) |
|
-- |
-- |
Checking-one office window has grills one does not-correct? 7/15 |
|
|
-- |
-- |
Two basement windows have grills-others (same side) do not 7/15 |
|
|
-- |
-- |
Rock facing like Lot 26? |
(per Curtis email July 16) |
|
-- |
-- |
Radon pipe location, size, routing concerns |
|
|
-- |
-- |
Missing grills in upstairs second bedroom |
|
|
-- |
-- |
Grills in downstairs bedroom should not be there |
Tom switch them |
|
-- |
-- |
Status and size of window in master bedroom? |
|
|
-- |
-- |
Change in location of floor vent in master bathroom? |
|
|
-- |
-- |
Status and size of window in master bathroom? |
Tom handling talking to Curtis windows/stone |
|
-- |
-- |
Heated floors? New electric box? 8/29 |
Heated floors appear installed. 11/7 |
|
-- |
-- |
Rockingham Petroleum? |
|
|
-- |
-- |
Rockingham Petroleum - Tues, Sept 15 |
|
|
-- |
-- |
Curtis wants a few "holes" in wood patched b/f insulation (see pics) |
|
|
-- |
-- |
When does the mantle need to go up? |
Curtis is asking 9/10/2020-mantle is up 9/30 |
|
-- |
-- |
Ital doing all floor tile |
|
|
-- |
-- |
Curtis email 9/15/2020 (Few Items) |
|
|
-- |
-- |
Need standard flooring quote (9/16/2020) |
|
|
-- |
-- |
Electric outlet above garage in storage area |
|
|
-- |
-- |
Add four foot double flourescent bulb centered in attic storage space |
|
|
-- |
-- |
Curtis email 9/17/2020 (Few Items) |
|
|
-- |
-- |
Harry needs in kitchen layout |
|
|
-- |
-- |
Exterior Chimney to be stone not stucco |
|
|
-- |
-- |
Rock ledges on false vents? |
|
|
-- |
-- |
Interior Wall Color = 0257 – Shortbread |
from Davis Paint Color Chart |
|
-- |
-- |
Scripture provided fan lights to go in second bedroom and basement bedroom |
|
|
-- |
-- |
Office IS taped/mudded 10/14 |
|
|
-- |
-- |
Microwave vent-does it need to be marked? |
|
|
-- |
-- |
Can we do handrails down both sides of the steps? |
Curtis wants this |
|
-- |
-- |
Awaiting decision on railings 10/29 |
|
|
-- |
-- |
Rock for fireplace scheduled for 11/2 |
Appears to be complete 11/7 |
|
-- |
-- |
Open up drywall at bottom of stairs |
|
|
-- |
-- |
Game plan for iron balusters? |
|
|
-- |
-- |
Game plan for shower door installation? |
Ron to install after closing. Door on order 12/8 GWB |
|
-- |
-- |
Paint garage door and front door to match shutters? |
Front door done 12/6 |
|
-- |
-- |
Stain steps before carpet runner |
Poly today, 12/7-appears complete 12/9 |
|
-- |
-- |
Dead bolt for safe room |
|
|
-- |
-- |
shave off bottom of safe room door |
Tom will have the trim guys do this |
|
-- |
-- |
cut trim behind living room cabinetry so it can be pushed against the wall |
|
|
-- |
-- |
touch up drywall at foyer alcoves |
Greg let Tim know to fix this |
|
-- |
-- |
door for linen closet? |
Installed. Just needs hardware. And shelving. |
|
-- |
-- |
220V for oven? |
Harry knows and will do. 12/6 |
|
-- |
-- |
CODED LOCKBOX 1010 |
|
|
-- |
-- |
Put numbers on mailbox |
John Weeks ON counter |
|
-- |
-- |
patio door hardware |
John Weeks |
|
-- |
-- |
|
|
|
-- |
-- |
Set fire Extinguisher |
John Weeks In pantry |
|
-- |
-- |
Touch up around wire near garage door |
John Weeks |
|
-- |
-- |
Shutters on side window? |
|
|
-- |
-- |
molding issue in main level bathroom? |
|
|
-- |
-- |
Granite need on single sink basement bath |
and laundry sink area |
|
-- |
-- |
Make another set of shutters |
Needs to be picked up and installed, Greg to pick up |
|
-- |
-- |
Light bulbs? |
Greg Ordered from Lowes. Getting 12/10 GWB |
|
-- |
-- |
|
|
|
-- |
-- |
Painting basement exterior doors? |
Greg will follow up with the painters |
|
-- |
-- |
Trim on bottom and edges of cabinets 12/13? |
Ital has. Donni coordinating with Curtis to install |
|
-- |
-- |
Crack in steps-issue? |
Tom will address |
|
-- |
-- |
Mailbox light |
Harry to install 1/11 needed photocell GWB |
|
-- |
-- |
Discuss accounting for gas line installation |
$250 from Jerry, $70 question from Curtis |
|
-- |
-- |
Mailbox light |
|
|
-- |
-- |
|
|
|
-- |
-- |
One towel holder needed (broken) |
Shanks is ordering a new one |
|
-- |
-- |
Garage door sensor wire request |
Greg to talk to Tom, electrician, etc. |
|
-- |
-- |
Low flow at kitchen sink |
Greg to talk to Tom about this |
|
-- |
-- |
|
|
|
-- |
-- |
Screens |
Just needed in garage |
|
-- |
-- |
Little touch-ups. Basement and kit ceilings |
|
|
-- |
-- |
Wine refrigerator |
end of January |
|
-- |
-- |
Move front outdoor faucet higher (Dry River) |
It looks like it moved up a little bit as there’s a fresh bead of silicone. GWB |
|
-- |
-- |
Repaint garage door |
Galindez Will paint. To coordinate with Curtis if needed GWB |
|
-- |
-- |
light/dark marks on concrete at front door where sealer was not applied correctly |
|
|
-- |
-- |
paint the inside of the PVC vents in front that vent furnace |
Galindez Will paint. To coordinate with Curtis if needed GWB |
|
-- |
-- |
paint/stain screw heads on shutters |
Galindez Will paint. To coordinate with Curtis if needed GWB |
|
-- |
-- |
install shutters under the deck |
onsite Kenny to install. Tom send Kenny over |
|
-- |
-- |
get 28-40 screen for garage |
Tom had extra one. To bring to curtis and install GWB |
|
-- |
-- |
electric receptacle needed in laundry room |
Greg will ask Harry for an update |
|
-- |
-- |
dent on top right side of washing machine |
|
|
-- |
-- |
Receptacle needed in pantry (dealing with Harry directly) |
|
|
-- |
-- |
Remove tape off lights in closet |
|
|
-- |
-- |
install pieces timber tech over screen door (Tom has/Kenny will install) |
|
|
-- |
-- |
paint ripped edges of timber tech boards on deck post at railing |
|
|
-- |
-- |
some Anderson windows in dining room have silicone in the corners from when constructed-needs to be cut out |
|
|
-- |
-- |
dining room has ceiling fan with light, but only one switch. Needs switch with speed control installed. |
|
|
-- |
-- |
Dimmer on light in alcove by front door |
|
|
-- |
-- |
needs stucco color caulk around front door |
There is a bead of caulk but I am not sure that it is a direct match. |
|
-- |
-- |
wash outside of the arch top window in MB |
|
|
-- |
-- |
hall bath mirror has a scratch in it |
Greg will talk to Ron |
|
-- |
-- |
towel bar in basement bath needs installed |
Amy to get to Ron to install GWB week of 1/11 |
|
-- |
-- |
need door stop mounted to floor for door that goes to the gun safe closet |
|
|
-- |
-- |
put longer pull cord on light under steps |
|
|
-- |
-- |
touch up paint throughout house marked with tape. (may have been completed 12/30?) |
|
|
-- |
-- |
Oak rail going down steps needs sanding |
|
|
-- |
-- |
put sconce light on wall in basement behind steps instead of snap light. |
|
|
-- |
-- |
cut off rebar grounding rod closer to the floor |
|
|
-- |
-- |
label gas valves in basement |
|
|
-- |
-- |
label gas valves in basement |
|
|
-- |
-- |
move switch behind door going into storage room in basement to rec. room side |
|
|
-- |
-- |
Extra paint? |
Kate will talk to the painter |
|
-- |
-- |
Return shingles |
Tom will deliver some shingles |
|
-- |
-- |
Painter to deliver extra touch up paint |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
setting for tomorrow 3/19 pending the check for the permits |
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
ordering week of june 22 |
|
-- |
-- |
Framing II (8) |
in process 5/25 |
|
-- |
-- |
Framing III (8) * |
Kate to reach out once framing is complete |
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
some installed 6/18 |
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
almost complete 6/10 |
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Order Appliances (0) |
|
|
-- |
-- |
Deck (0) |
In process 11/7 |
|
-- |
-- |
Gutters (0) |
11/9 |
|
-- |
-- |
Driveway (0) |
formed 10/24 |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
11/9 |
|
-- |
-- |
HVAC Rough In (4) |
In process 7/15 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Sept 3 |
|
-- |
-- |
Plumbing Rough In (4) |
Complete except large tub in master 9/2 |
|
-- |
-- |
Electric Rough In (4) |
In process 7/29 |
|
-- |
-- |
Exterior Vinyl (0) * |
Almost complete 11/4 |
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
Friday, September 25 |
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Completed except for decorative shelf 10/21 |
|
-- |
-- |
Paint 1 (1) |
|
|
-- |
-- |
Garage Door (0) |
has been ordered 6/25 |
|
-- |
-- |
House Numbers (0) |
Just house numbers |
|
-- |
-- |
Cabinet Installation (2) * |
All but setting tv center seems complete 11/29 |
|
-- |
-- |
Granite Installation (1) * |
All but basement single sink 12/6 |
|
-- |
-- |
Interior Trim - Install (3) |
Almost complete 11/4 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Grouting floors 11/13 - Tile shower 11/14 per Cyndi GWB |
|
-- |
-- |
Paint 2 (3) |
In process 11/29 |
|
-- |
-- |
Cover Floors (1) |
Partially 11/15 |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
November 13 plumbing |
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
in process 12/9. Need towel bars/toilet paper holders/towel rings 12/9 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
Greg will get check from Tina |
|
-- |
-- |
Set Water Meter (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
In process 12/6 |
|
-- |
-- |
HVAC Trim Out (1) |
Friday, Nov 20 |
|
-- |
-- |
Plumbing Trim Out (2) |
In process 12/6 |
|
-- |
-- |
Install Appliances (0) * |
Mon, Dec 7 |
|
-- |
-- |
Paint 3 (2) * |
In process 12/9-just needs touched up-Greg will blue tape GWB |
|
-- |
-- |
Carpet (2) |
Wednesday, Dec 2 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
Afternoon of Monday, Dec 14 |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
in process 12/19 |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
December 29 |
|
-- |
-- |
Buyer Walk Through (1) |
|
|
-- |
-- |
Payment for Upgrades (0) |
|
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) |
|
|
-- |
-- |
Closing (1) |
Tuesday, December 29th at 3:00 PM |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|