Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
--   --   Discuss Existing Conduit Layout
--   --   Shingle color? Same?
--   --   Shingle color? Same?
--   --  
--   --   Busted back pillar 6/24 Wrap with white PVC board
--   --   Photo of framed opening: https://bit.ly/2PojUVs
--   --   Electric trim out before remaining drywall goes up 8/19
--   --   Kate - Can the buyer pick the LVP color?
--   --   Kate - Can the buyer extend LBP to the bedrooms?
--   --   Kate - The buyer is ready to pick the granite color.
--   --   Bathroom floors-arriving 10/29 Eric to install 11/6in process 11/7
--   --   CODED LOCKBOX 0101
--   --   Anchor dishwasher 11/29
--   --   Drywall repairs needed
--   --   Door lock broken 12/16
--   --   Door lock broken 12/16
--   --  
--   --   Window framing repairs needed in MB 1/3 Painter
--   --   Light bulbs needed throughout 1/6 Greg to order and put in GWB
--   --   Paint touch up needed throughout
--   --   Transition strip to laundry needed 1/20 Greg to get from lowes 1/21 Eric to install
--   --   Microwave needed Maybe on order?
--   --   Cabinet trim needed in hallway bath 2/3
--   --   Clean again is it going to need it again?? 2/14
--   --   Paint door trim 2/6 Needs completing 2/24
--   --   Door handle to patio door needed 2/6
--   --   Bathroom outlet covers needed 2/10 after paint touch up 2/14
--   --   Check deadbolt Broken 2/17
--   --   Landscaping repairs 3/3 Tom scheduling landscaping 3/18
--   --   Loose door handle Kate talked to Ron-
--   --   Deadbolt is difficult to operate WD40-worked better 3/31
--   --   Touch up paint
--   --   Paint front door
--   --   Pressure wash siding
--   --   Finish cable panel Tom will take a look
--   --   Final clean
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)       Jan 6 or 7
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 2/8
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        Roof in process 3/29
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       in process 4/4
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 4/29
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Almost complete 6/14
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Doors ordered. Trim to be ordered 9/28 GWB
-- -- Drywall (Hang) (4) *        Almost complete 9/2
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 9/19- almost completed
-- -- Paint 1 (1)       Set to start 9/22 GWB
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Thursday, 11/11
-- -- Interior Trim - Install (3) *        in process 10/14
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Waiting on arrival date for that flooring.
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Galindez on site 11/5 should be finished
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In process 11/7
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        In process 1/3
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *       
-- -- Install Appliances (0) *        CJ to install pending date
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)       1.22 GWB
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Tuesday, 4/20 at 11AM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       Wed, 4/21 at 4:00 PM
-- -- Closing (1)       Wed, 4/21 at 4:30 PM