- 2  ::  1280 Constitution Court #104
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX --- 9593 Or 9074
--   --   Broken window
--   --   Cleaning
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Order Appliances (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Order Plumbing / Lighting Fixtures (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Set Water Meter (0) *       
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Schedule Closing (0)      
Tue    Dec 30      Keys to Settlement Agent (0)      
Tue    Dec 30      Review Settlement Statement (0)      
Tue    Dec 30      Jerry Signs Closing Documents (0)      
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
Tue    Dec 30      Closing (1)      
Wed    Dec 31      Remove Coded Lockbox (0)      
--   --   Remove furniture, etc.
--   --   Install all heat registers
--   --   Move clock and table to Townes 105
--   --   Move clock to Jerry's house, table to Townes 105
--   --   Trim guy confused on a Cole of doors
--   --   Trim guy confused on a couple of doors
--   --   Remove stuff Kate will coordinate with Tom ASAP
--   --   Patch drywall on ceiling Interior Finishing
--   --   Touch up paint Isaac
--   --   Install bathroom vanity Alex
--   --   Repair sliding glass door Osbaldo
--   --   Repair master bedroom window Osbaldo
--   --   Check temperature at master bathroom shower Osbaldo - check on it
--   --   Install weather stripping at front door Osbaldo
--   --   Remove ladder Osbaldo
--   --   Fix four way light switch Alex
--   --   Install side splash
--   --   Add receptacle for microwave Tom
--   --   Move pillows to storage container Osbaldo
--   --   Install bed skirt on master bed Osbaldo
--   --   Install screens Tom will pick up and install
--   --   Move furniture to Heritage 5 Tues, Apr 3
--   --   Extend downspouts away from building Tom
--   --   Install filter in the plenum at the furnace
--   --   Make auxiliary heat work at the thermostat Ronnie is thinking about it
--   --   Flip laundry connection box right side up and swap hot/cold indicators ??????
--   --   Adjust bathroom vanity top installation with gaps between wall Osbaldo - caulk
--   --   Install missing vent fan cover in bathroom Ronnie
--   --   Repair exterior vent where grill is missing and flapper is stuck open. A bird was flying in/out - Tom
--   --   Adjust main entry strike plate so that the door will lock properly Dead bolt
--   --   Repair or replace master bedroom window - tilt lock mechanism not working properly Has arrived
--   --   Install missing shoe molding behind the toilet and between tub and vanity Tom
--   --   Touch up paint Kate will touch base with Isaac
--   --   Alert Suzanne that (when) all repairs are complete On order from Mongers
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery Dec 2, Installation Dec 5
-- -- Granite Installation (1) *        Thurs Dec 15
-- -- Interior Trim - Install (3) *        11/28 will be complete today.
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *       
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *       
-- -- Install Appliances (0) *       
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Tomorrow 4/24 at 10am
-- -- Payment for Upgrades (0)