- 201  ::  1270 Constitution Court #201
[ BUILD: 1805-0144 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
--   --   Electric trim out before final drywall 8/19
--   --   Kitchen needs painted 10/17
--   --   Flooring transition strips needed 10/17
--   --   Redo floor in Bath/laundry Eagle to lay 10/26 GWB
--   --   Cabinet hardware Midsouth Scheduling/ waiting on confirmed date
--   --   Drywall repairs 10/28 Tim to finish by 11/7
--   --   Bathroom trim needs installing 10/29
--   --   Pain door/trim 10/31
--   --   CODED LOCKBOX 0201
--   --  
--   --   Hook up water heater Harry Knows
--   --   Finish bathroom fan Harry knows
--   --   Screens
--   --   Final clean Kelly over weekend of 11/7 GWB
--   --   Paint over drywall patch Mahar set to come Monday 11/9
--   --   Remove orange sprinkler head in MB sprinkler people - Tom will contact
--   --   Outside light does not stay on
--   --   Patch drywall at sprinkler head
--   --   Remove items in living room
--   --   Condo unit outdoor lights Harry has the lights and needs to install them
--   --   LIght bulb needed in MB bathroom - Greg
--   --   Electric outlet-MB wiring exposed-cable? needs blank cover - Greg
--   --   Final test on sprinkler
--   --   Get heat up and running in all units Still need to set three more units
--   --  
--   --   Molding in closet needed Quarter round - Greg will talk to Majer
--   --   Toilet paper holder/clean completed 12/2
--   --   Protective film needs to be removed on deck white board trim completed
--   --   black paper sticking out underneath the patio door Kenny said he was fixing 2/3
--   --   Carpet/Trash on Deck completed
--   --   remove yellow caps off smoke detectors Greg will try to get this
--   --   nail down deck board/nails on front walkway Rick
--   --   remove housewrap from front windows Davenport
--   --   patch drywall around sprinkers Greg will talk to Majer
--   --   final touch up paint Blue taped and Mahar knows.
--   --   Fill nail holes at trim around windows set in rock Davenport
--   --   Drywall patch behind toilet in MB Galindez to touch up this week GWB
--   --   Caulk from tile/tub
--   --   gutter repairs
--   --  
--   --   Eagle-small piece missing flooring near patio 12/13
--   --   Front door handle is loose 12/13
--   --   Remove old sign posts 12/13
--   --  
--   --  
--   --   Cover on sprinkler head in MB
--   --   Crack/line in LR wall 1/13 Greg to blue tape
--   --   Front door handle loose 1/13 Ron to fix when he installs the next unit
--   --   Kelly reclean condo before walkthrough
--   --   Kelly to clean condo before walkthrough
--   --   Touch up paint Court has blue taped issues 1/23
--   --   Bill Tolbert, Lumos, 540-437-1206
--   --   Remove plastic from window 2/6
--   --   Dumpster
--   --   Fence by dumpster In process 2/17
--   --   MOVING MODEL TODAY AND CLEANING OVER WEEKEND
--   --   Paint touch up
--   --   Remove protective film from outside band board
--   --   Combo lock-repair? Replace?
--   --   Manuals needed 2/14
--   --   Patch and paint holes from wall hangings
--   --   Paint touch ups throughout pay special attention to areas at front door inside that need caulk and touch up Painter
--   --   Adjust master bath door Tom - does not lock
--   --   Cabinet drawer in hall bath needs adjusting
--   --   Left front bedroom window addressed drop lock on the right Lock to be adjusted
--   --   Order new fixed panel drawer at kitchen sink scratches that paint touch up doesn’t fix On site, ready for Tom to install
--   --   Drill hole through side of island....Tom how to fix? Back out screw a bit
--   --   Paint front door and trim
--   --   aanita0417@gmail.com 540 421 6486
--   --   Front door lock problem
--   --   One window does not lock Tom
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Almost complete 6/14
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Doors ordered. trim set to deliver 9/23 GWB
-- -- Drywall (Hang) (4) *        In process 9/2
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 9/13
-- -- Paint 1 (1)       Set to start 9/21 GWB
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Set for 10/2 GWB
-- -- Interior Trim - Install (3) *        in process 9/30
-- -- Order Plumbing / Lighting Fixtures (0)       On site 10/28
-- -- Luxury Vinyl Plank (3) *        To start on Oct 1-in process 10/3
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       On site 10/10
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Need mirrors 11/4
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *        Main sprinkler valve connected. City to come 11/5 to turn on water
-- -- Electric Trim Out (3) *        almost complete 10/29
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Plumbers on site and installing 11/4
-- -- Install Appliances (0) *       
-- -- Paint 3 (2) *        Scheduled for 10/26 GWB
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Waiting on sprinkler guy to connect with fire marshall
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Friday, Feb 26 at 1:00 PM;
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       Stewart Title
-- -- Closing (1)       Mar 3 at 10:00 AM;
-- -- Remove Coded Lockbox (0)