Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Building Permit (30) *       
Mon    Jan 26      Order Roof & Floor Trusses (1)      
Tue    Jan 27      Order Windows & Doors (0)      
Tue    Jan 27      Stake Out Home (1)      
Wed    Jan 28      Excavate (2)      
Fri    Jan 30      Inspection (Footers) (1)      
Mon    Feb 2      Inspection (Concrete Wall) (1)      
Tue    Feb 3      Pour Footers (1) *       
Wed    Feb 4      Set Forms (2)      
Fri    Feb 6      Pour Foundation Walls (1)      
Mon    Feb 9      Plumb Slab (2)      
Wed    Feb 11      Inspection (Plumbing Under Slab) (1)      
Thu    Feb 12      Inspection (Conduit Under Slab) (1)      
Fri    Feb 13      Prepare Slab (1)      
Mon    Feb 16      Inspection (Slab) (1)      
Tue    Feb 17      Inspection (Drain Tile) (0)      
Tue    Feb 17      Pour Slab (1) *       
Wed    Feb 18      Settlement Agent Confirmed (0)      
Wed    Feb 18      Framing I (9)      
Tue    Mar 3      Order Steps (0)      
Tue    Mar 3      Order Tubs / Showers (0)      
Tue    Mar 3      Framing II (8)      
Fri    Mar 13      Framing III (8) *       
Wed    Mar 25      Verify Window & Roof Structure (0)      
Wed    Mar 25      Install Stairs (0) *       
Wed    Mar 25      Windows & Doors (0) *       
Wed    Mar 25      House Number and Status in Window (0)      
Wed    Mar 25      Roofing (0) *       
Wed    Mar 25      Order Cabinets (0)      
Wed    Mar 25      Order Appliances (0)      
Wed    Mar 25      Deck (0)      
Wed    Mar 25      Gutters (0)      
Wed    Mar 25      Driveway (0) *       
Wed    Mar 25      Patio (0)      
Wed    Mar 25      Privacy Divider / Fence (0) *       
Wed    Mar 25      Sod / Seed / Landscaping (0)      
Wed    Mar 25      HVAC Rough In (4)      
Tue    Mar 31      Rough In Microwave Vent (0)      
Tue    Mar 31      Plumbing Rough In (4)      
Mon    Apr 6      Electric Rough In (4)      
Fri    Apr 10      Inspection (Rough In HVAC) (1)      
Mon    Apr 13      Inspection (Rough In Plumbing) (1)      
Tue    Apr 14      Inspection (Rough In Electric) (1)      
Wed    Apr 15      Inspection (Framing) (1) *       
Thu    Apr 16      Inspection (Deck Piers) (0)      
Thu    Apr 16      Exterior Vinyl (0) *       
Thu    Apr 16      Exterior Stone (0)      
Thu    Apr 16      Insulation (2) *       
Mon    Apr 20      Inspection (Insulation) (1)      
Tue    Apr 21      Inspection (Electric Service) (0)      
Tue    Apr 21      Set Electric Meter (0) *       
Tue    Apr 21      Inspection (Main Sewer Line) (0)      
Tue    Apr 21      Inspection (Main Water Line) (0)      
Tue    Apr 21      Order Interior Doors & Trim (0)      
Tue    Apr 21      Drywall (Hang) (4) *       
Mon    Apr 27      Loan Approval (0)      
Mon    Apr 27      Deed Preparation (0)      
Mon    Apr 27      Drywall (Tape, Block, Skim, Sand) (6) *       
Tue    May 5      Paint 1 (1)      
Wed    May 6      Garage Door (0)      
Wed    May 6      House Numbers (0)      
Wed    May 6      Mailbox (0)      
Wed    May 6      Cabinet Installation (2) *       
Fri    May 8      Granite Installation (1) *       
Mon    May 11      Interior Trim - Install (3) *       
Thu    May 14      Order Plumbing / Lighting Fixtures (0)      
Thu    May 14      Interior Trim - Paint (1)      
Fri    May 15      Luxury Vinyl Plank (3) *       
Wed    May 20      Luxury Vinyl Tile (0)      
Wed    May 20      Paint 2 (3)      
Mon    May 25      Cover Floors (1)      
Tue    May 26      Deliver Plumbing / Lighting Fixtures (0)      
Tue    May 26      Shoe Moulding (0)      
Tue    May 26      Shelving, Door Knobs, Fire Extinguisher (0) *       
Tue    May 26      Install Coded Lockbox (add extra keys) (0)      
Tue    May 26      Pay Water / Sewer Taps (0)      
Tue    May 26      Set Water Meter (0) *       
Tue    May 26      Electric Trim Out (3) *       
Fri    May 29      Ceiling Fans (0)      
Fri    May 29      HVAC Trim Out (1) *       
Mon    Jun 1      Blower Door Test (1)      
Tue    Jun 2      Plumbing Trim Out (2) *       
Thu    Jun 4      Install Appliances (0) *       
Thu    Jun 4      Paint 3 (2) *       
Mon    Jun 8      Carpet (2)      
Wed    Jun 10      Appraiser Confirms Construction Completion (0)      
Wed    Jun 10      Inspection (Final HVAC) (1)      
Thu    Jun 11      Inspection (Final Plumbing) (1)      
Fri    Jun 12      Inspection (Final Electric) (1)      
Mon    Jun 15      Inspection (Final Building) (2) *       
Wed    Jun 17      Pre Walk Through (0)      
Wed    Jun 17      Stain Hardwood Stairs (1) *       
Thu    Jun 18      Cleaning (1)      
Fri    Jun 19      Certificate of Occupancy (1) *       
Mon    Jun 22      C.O. to Lender (0)      
Mon    Jun 22      Schedule Closing (0)      
Mon    Jun 22      Buyer Walk Through (1) *       
Tue    Jun 23      Payment for Upgrades (0)      
Tue    Jun 23      Keys to Settlement Agent (0)      
Tue    Jun 23      Review Settlement Statement (0)      
Tue    Jun 23      Jerry Signs Closing Documents (0)      
Tue    Jun 23      Request Trash Tote From POA Manager (0)      
Tue    Jun 23      Closing (1)      
Wed    Jun 24      Remove Coded Lockbox (0)