- 2  ::  1280 Constitution Court #302
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Need white De Soto and Coco touch up kits for kitchen and bathroom cabinetry Ordered, will be dropped off at the property
--   --   Tom adjust vinyl ceiling Greg - at front door
--   --   Buff countertop in second bathroom At warehouse, Mindy will coordinate install
--   --   CODED LOCKBOX --- 4625
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Order Tubs / Showers (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Install Stairs (0) *       
Wed    Dec 17      House Number and Status in Window (0)      
Wed    Dec 17      Order Appliances (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Garage Door (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Order Plumbing / Lighting Fixtures (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Shoe Moulding (0)      
Tue    Dec 23      Set Water Meter (0) *       
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Paint 3 (2) *       
Fri    Dec 26      Inspection (Final HVAC) (1)      
Mon    Dec 29      Inspection (Final Plumbing) (1)      
Tue    Dec 30      Inspection (Final Electric) (1)      
Wed    Dec 31      Stain Hardwood Stairs (1) *       
Thu    Jan 1      Schedule Closing (0)      
Thu    Jan 1      Payment for Upgrades (0)      
Thu    Jan 1      Keys to Settlement Agent (0)      
Thu    Jan 1      Review Settlement Statement (0)      
Thu    Jan 1      Jerry Signs Closing Documents (0)      
Thu    Jan 1      Request Trash Tote From POA Manager (0)      
Thu    Jan 1      Remove Coded Lockbox (0)      
--   --   Patch / Paint at Railing to Loft
--   --   Thorough Cleaning
--   --   Add screen at ridge vent
--   --   Remove furnishings Take to 104
--   --   Replace water filter in refrigerator. See red light. Waiting on Fergusons to supply
--   --   Touch up staining on the steps and boards leading up to front door HOA
--   --   Paint touch up Isaac Monday 8/7
--   --   Laminate floor touch up. Several scratches. Eric
--   --   I just trim at miter on attic access panel in loft
--   --   Adjust trim at miter is n up loft panel Tom
--   --  
--   --   Replace filter
--   --   Clean off siding on deck Tom
--   --   Bath countertop in second bathroom
--   --   I just crooked fan in second bathroom Tom
--   --   Water sealant on deck Isaac
--   --   Chain on utility door on deck
--   --   Change door locks
--   --   Install fanin master and not flush mount Tom
--   --   Blue x near front door buyer says floor has too much give Eric
--   --   AC not working properly? Ronnie
--   --   Replace air filter Ronnie
--   --   Remove selections from front bedroom
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *       
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *       
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *       
-- -- Install Appliances (0) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Final Wednesday 8/9
-- -- Closing (1)       THURSDAY, AUG 10