| -- | -- | Need white De Soto and Coco touch up kits for kitchen and bathroom cabinetry | Ordered, will be dropped off at the property | |
| -- | -- | Tom adjust vinyl ceiling | Greg - at front door | |
| -- | -- | Buff countertop in second bathroom | At warehouse, Mindy will coordinate install | |
| -- | -- | CODED LOCKBOX --- 4625 | ||
| Mon | Dec 15 | Ratified Contract? (0) | ||
| Mon | Dec 15 | $2500 Deposit Received (0) | ||
| Mon | Dec 15 | Association Packet Requested (0) | ||
| Mon | Dec 15 | Association Packet Received (0) | ||
| Mon | Dec 15 | Selections Meeting (0) | ||
| Mon | Dec 15 | Selections Sheet Signed (0) | ||
| Mon | Dec 15 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Mon | Dec 15 | Deposit For Upgrades Received (0) | ||
| Mon | Dec 15 | Inspection (Concrete Wall) (1) | ||
| Tue | Dec 16 | Inspection (Conduit Under Slab) (1) | ||
| Wed | Dec 17 | Inspection (Drain Tile) (0) | ||
| Wed | Dec 17 | Settlement Agent Confirmed (0) | ||
| Wed | Dec 17 | Order Tubs / Showers (0) | ||
| Wed | Dec 17 | Verify Window & Roof Structure (0) | ||
| Wed | Dec 17 | Install Stairs (0) * | ||
| Wed | Dec 17 | House Number and Status in Window (0) | ||
| Wed | Dec 17 | Order Appliances (0) | ||
| Wed | Dec 17 | Patio (0) | ||
| Wed | Dec 17 | Rough In Microwave Vent (0) | ||
| Wed | Dec 17 | Inspection (Rough In Plumbing) (1) | ||
| Thu | Dec 18 | Inspection (Rough In Electric) (1) | ||
| Fri | Dec 19 | Inspection (Framing) (1) * | ||
| Mon | Dec 22 | Inspection (Deck Piers) (0) | ||
| Mon | Dec 22 | Exterior Stone (0) | ||
| Mon | Dec 22 | Set Electric Meter (0) * | ||
| Mon | Dec 22 | Inspection (Main Water Line) (0) | ||
| Mon | Dec 22 | Loan Approval (0) | ||
| Mon | Dec 22 | Deed Preparation (0) | ||
| Mon | Dec 22 | Garage Door (0) | ||
| Mon | Dec 22 | Mailbox (0) | ||
| Mon | Dec 22 | Order Plumbing / Lighting Fixtures (0) | ||
| Mon | Dec 22 | Interior Trim - Paint (1) | ||
| Tue | Dec 23 | Deliver Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Shoe Moulding (0) | ||
| Tue | Dec 23 | Set Water Meter (0) * | ||
| Tue | Dec 23 | Ceiling Fans (0) | ||
| Tue | Dec 23 | Blower Door Test (1) | ||
| Wed | Dec 24 | Paint 3 (2) * | ||
| Fri | Dec 26 | Inspection (Final HVAC) (1) | ||
| Mon | Dec 29 | Inspection (Final Plumbing) (1) | ||
| Tue | Dec 30 | Inspection (Final Electric) (1) | ||
| Wed | Dec 31 | Stain Hardwood Stairs (1) * | ||
| Thu | Jan 1 | Schedule Closing (0) | ||
| Thu | Jan 1 | Payment for Upgrades (0) | ||
| Thu | Jan 1 | Keys to Settlement Agent (0) | ||
| Thu | Jan 1 | Review Settlement Statement (0) | ||
| Thu | Jan 1 | Jerry Signs Closing Documents (0) | ||
| Thu | Jan 1 | Request Trash Tote From POA Manager (0) | ||
| Thu | Jan 1 | Remove Coded Lockbox (0) | ||
| -- | -- | Patch / Paint at Railing to Loft | ||
| -- | -- | Thorough Cleaning | ||
| -- | -- | Add screen at ridge vent | ||
| -- | -- | Remove furnishings | Take to 104 | |
| -- | -- | Replace water filter in refrigerator. See red light. | Waiting on Fergusons to supply | |
| -- | -- | Touch up staining on the steps and boards leading up to front door | HOA | |
| -- | -- | Paint touch up | Isaac Monday 8/7 | |
| -- | -- | Laminate floor touch up. Several scratches. | Eric | |
| -- | -- | I just trim at miter on attic access panel in loft | ||
| -- | -- | Adjust trim at miter is n up loft panel | Tom | |
| -- | -- | |||
| -- | -- | Replace filter | ||
| -- | -- | Clean off siding on deck | Tom | |
| -- | -- | Bath countertop in second bathroom | ||
| -- | -- | I just crooked fan in second bathroom | Tom | |
| -- | -- | Water sealant on deck | Isaac | |
| -- | -- | Chain on utility door on deck | ||
| -- | -- | Change door locks | ||
| -- | -- | Install fanin master and not flush mount | Tom | |
| -- | -- | Blue x near front door buyer says floor has too much give | Eric | |
| -- | -- | AC not working properly? | Ronnie | |
| -- | -- | Replace air filter | Ronnie | |
| -- | -- | Remove selections from front bedroom | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | ||
| -- | -- | Electric Rough In (4) | ||
| -- | -- | Inspection (Rough In HVAC) (1) | ||
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | ||
| -- | -- | Paint 1 (1) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | ||
| -- | -- | Granite Installation (1) * | ||
| -- | -- | Interior Trim - Install (3) * | ||
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | ||
| -- | -- | Paint 2 (3) | ||
| -- | -- | Cover Floors (1) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | ||
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Electric Trim Out (3) * | ||
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | ||
| -- | -- | Install Appliances (0) * | ||
| -- | -- | Carpet (2) | ||
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | ||
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | ||
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Buyer Walk Through (1) * | Final Wednesday 8/9 | |
| -- | -- | Closing (1) | THURSDAY, AUG 10 | |