- 2  ::  1280 Constitution Court #302
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Need white De Soto and Coco touch up kits for kitchen and bathroom cabinetry Ordered, will be dropped off at the property
--   --   Tom adjust vinyl ceiling Greg - at front door
--   --   Buff countertop in second bathroom At warehouse, Mindy will coordinate install
--   --   CODED LOCKBOX --- 4625
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Order Tubs / Showers (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Install Stairs (0)      
Thu    May 1      House Number and Status in Window (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Garage Door (0) *       
Tue    May 6      Mailbox (0)      
Tue    May 6      Order Plumbing / Lighting Fixtures (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Deliver Plumbing / Lighting Fixtures (0)      
Wed    May 7      Shoe Moulding (0)      
Wed    May 7      Set Water Meter (0) *       
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Paint 3 (2) *       
Mon    May 12      Inspection (Final HVAC) (1)      
Tue    May 13      Inspection (Final Plumbing) (1)      
Wed    May 14      Inspection (Final Electric) (1)      
Thu    May 15      Stain Hardwood Stairs (1)      
Fri    May 16      Schedule Closing (0)      
Fri    May 16      Payment for Upgrades (0)      
Fri    May 16      Keys to Settlement Agent (0)      
Fri    May 16      Review Settlement Statement (0)      
Fri    May 16      Jerry Signs Closing Documents (0)      
Fri    May 16      Request Trash Tote From POA Manager (0)      
Fri    May 16      Remove Coded Lockbox (0)      
--   --   Patch / Paint at Railing to Loft
--   --   Thorough Cleaning
--   --   Add screen at ridge vent
--   --   Remove furnishings Take to 104
--   --   Replace water filter in refrigerator. See red light. Waiting on Fergusons to supply
--   --   Touch up staining on the steps and boards leading up to front door HOA
--   --   Paint touch up Isaac Monday 8/7
--   --   Laminate floor touch up. Several scratches. Eric
--   --   I just trim at miter on attic access panel in loft
--   --   Adjust trim at miter is n up loft panel Tom
--   --  
--   --   Replace filter
--   --   Clean off siding on deck Tom
--   --   Bath countertop in second bathroom
--   --   I just crooked fan in second bathroom Tom
--   --   Water sealant on deck Isaac
--   --   Chain on utility door on deck
--   --   Change door locks
--   --   Install fanin master and not flush mount Tom
--   --   Blue x near front door buyer says floor has too much give Eric
--   --   AC not working properly? Ronnie
--   --   Replace air filter Ronnie
--   --   Remove selections from front bedroom
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *       
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)      
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Final Wednesday 8/9
-- -- Closing (1)       THURSDAY, AUG 10