| Mon | Dec 15 | Ratified Contract? (0) | ||
| Mon | Dec 15 | $2500 Deposit Received (0) | ||
| Mon | Dec 15 | Association Packet Requested (0) | ||
| Mon | Dec 15 | Association Packet Received (0) | ||
| Mon | Dec 15 | Selections Meeting (0) | ||
| Mon | Dec 15 | Selections Sheet Signed (0) | ||
| Mon | Dec 15 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Mon | Dec 15 | Deposit For Upgrades Received (0) | ||
| Mon | Dec 15 | Inspection (Concrete Wall) (1) | ||
| Tue | Dec 16 | Inspection (Conduit Under Slab) (1) | ||
| Wed | Dec 17 | Inspection (Drain Tile) (0) | ||
| Wed | Dec 17 | Settlement Agent Confirmed (0) | ||
| Wed | Dec 17 | Verify Window & Roof Structure (0) | ||
| Wed | Dec 17 | Patio (0) | ||
| Wed | Dec 17 | Rough In Microwave Vent (0) | ||
| Wed | Dec 17 | Inspection (Rough In Plumbing) (1) | ||
| Thu | Dec 18 | Inspection (Rough In Electric) (1) | ||
| Fri | Dec 19 | Inspection (Framing) (1) * | ||
| Mon | Dec 22 | Inspection (Deck Piers) (0) | ||
| Mon | Dec 22 | Exterior Stone (0) | ||
| Mon | Dec 22 | Set Electric Meter (0) * | ||
| Mon | Dec 22 | Inspection (Main Water Line) (0) | ||
| Mon | Dec 22 | Loan Approval (0) | ||
| Mon | Dec 22 | Deed Preparation (0) | ||
| Mon | Dec 22 | Mailbox (0) | ||
| Mon | Dec 22 | Interior Trim - Paint (1) | ||
| Tue | Dec 23 | Ceiling Fans (0) | ||
| Tue | Dec 23 | Blower Door Test (1) | ||
| Wed | Dec 24 | Inspection (Final HVAC) (1) | ||
| Thu | Dec 25 | Inspection (Final Plumbing) (1) | ||
| Fri | Dec 26 | Inspection (Final Electric) (1) | ||
| Mon | Dec 29 | Stain Hardwood Stairs (1) * | ||
| Tue | Dec 30 | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Needs final drywall sanding 11/4 | ||
| -- | -- | CODED LOCKBOX 0203 | ||
| -- | -- | Sprinkler issue? 1/23 | Drywall repair needed | |
| -- | -- | Missing door? 1/23 | Tom will ask for it to be delivered-in living room | |
| -- | -- | I think the numbers say 302 outside the door | Tom or Jill | |
| -- | -- | Fridge in unit-correct fridge?? | ||
| -- | -- | Bathroom sink tops | Kate is waiting to hear from Kimberly | |
| -- | -- | Paint front door 2/24 | ||
| -- | -- | Vanity lights and outlet covers | Harry-he told me his working Saturday to do this 3/3 | |
| -- | -- | Snap light over shower | Harry-not one 2/27 | |
| -- | -- | Paint - is it the correct color? | ||
| -- | -- | French style fridge is in kitchen 2/27 | ||
| -- | -- | Cabinet floor trim needed 3/3 | On top of cabinets just needs cut/installed | |
| -- | -- | Home Inspection - Wed, Mar 10 @ 9AM | Rudy Long | |
| -- | -- | Screens needed | ||
| -- | -- | Fix missing part of dishwasher | ||
| -- | -- | Caulk MB sink top backsplash | Painter-needs caulk at bottom of backsplash 3/17isilicone? | |
| -- | -- | Cover electrical box | Jill | |
| -- | -- | Remove extra supplies from top of kitchen cabinets | And back deck | |
| -- | -- | Nail needed in extra shoe molding | ||
| -- | -- | Increase cold water pressure on left master bath sink | Fixing 3/18-Tom | |
| -- | -- | Make the dishwasher work (did not work during inspection) | CJ taking care of today 3/18 | |
| -- | -- | Install weatherstripping at the front door to close gaps | Painter | |
| -- | -- | Secure half bathroom sink top with a wedge (?) | ||
| -- | -- | Pressure wash front window? Dirt/concrete | ||
| -- | -- | Change type of dryer outlet? | From the buyer - The bottom prong that I have is an L shape and the outlet has a circle there | |
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| Upgraded Gray Shaker Kitchen Cabinets (cost included in contract price) | ||||
| Level III Granite Kitchen Countertops (cost included in contract price) | ||||
| French style refrigerator (cost included in contract price) | ||||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | Hopefully week of Jan 18 | |
| -- | -- | Order Appliances (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | ||
| -- | -- | Electric Rough In (4) | In process 7/12 | |
| -- | -- | Inspection (Rough In HVAC) (1) | ||
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | Stocked 9/19 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | In process 10/24 | |
| -- | -- | Paint 1 (1) | ||
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | Delivery Feb 15, install set for 2/16 GWB | |
| -- | -- | Granite Installation (1) * | Scheduled for Feb 17-in process 2/17 | |
| -- | -- | Interior Trim - Install (3) * | ||
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | In process 2/27 | |
| -- | -- | Luxury Vinyl Tile (0) | In process 2/27 | |
| -- | -- | Paint 2 (3) | Not completed 2/24-looks like whole house is chantilly lace | |
| -- | -- | Cover Floors (1) | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | Ready 3/3 | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | ||
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | In process 2/24 | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | Tomorrow morning 3/7 | |
| -- | -- | Install Appliances (0) * | Installed. Fridge needs pushed back 3/7 | |
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | In process 2/27 | |
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | Monday, March 8 | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | Kelly wants water | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | ||
| -- | -- | Buyer Walk Through (1) * | Tuesday 3/16 at 4:00 PM | |
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Closing (1) | Fri, Mar 19 @ 1:30 PM (for the buyer) | |
| -- | -- | Remove Coded Lockbox (0) | ||