- 202  ::  1270 Constitution Court #202
[ BUILD: 1805-0145 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
--   --   Electric rough in -final 8/30
--   --   CODED LOCKBOX 0202
--   --   Loose screws on decking boards on 2nd and 3rd towers
--   --   Whole house chantilly?
--   --   Silver bedroom light ok? Rest is black. Not completed 5/15
--   --   Remove old sign posts
--   --   New dumpster
--   --   Remove protective film from outside band board
--   --   Ceiling drywall repairs 3/24
--   --   Fridge handles?
--   --   Paint front door
--   --   Caulk in front of tubs Jill has lined up for Monday 6/21
--   --   Touch up paint throughout 5/5
--   --   Drywallers arriving 6/17
--   --   Touch up needed M bath ceiling 6/23
--   --   Drywall touch up, paint touch up Monday, June 28
--   --   Drywall touch up/ paint indicated by blue tape
--   --   Fix showerhead escutcheon to wall
--   --   swap out the current front door lock system with a new system so that we start out with my daughter able to be fully safe
--   --   Raise front door light 18 inches
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
    Gray Shaker Kitchen Cabinets (cost included in contract price)  
    White Shaker Bathroom Cabinets (cost included in contract price)  
    Level III Quartz Countertops (cost included in contract price)  
    Farmhouse Style Plumbing Package (cost included in contract price)  
    Luxury Vinyl Plank in Both Bedrooms (cost included in contract price)  
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       Ordered and set to deliver 1/21
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       In process 5/25
-- -- Electric Rough In (4)       In process 6/17
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Stocked 9/19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Sanding 10/7
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Dec 29th From Kimberly GWB
-- -- Granite Installation (1) *        Feb 8
-- -- Interior Trim - Install (3) *        In process 11/11
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        In process 2/10
-- -- Luxury Vinyl Tile (0)       On site
-- -- Paint 2 (3)       Ready for this anytime
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In process 3/3
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process 3/24.
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Bathroom vanities not completed/outlet covers needed
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Supplies on site 3/3
-- -- Install Appliances (0) *        5/6?
-- -- Paint 3 (2) *       
-- -- Carpet (2)       NO Carpet
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)       Kate setting this up for the middle of next week
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Friday 25th at 1:00 PM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       6/28/2021 @ 11:30 AM
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       June 30
-- -- Remove Coded Lockbox (0)