- 202  ::  1270 Constitution Court #202
[ BUILD: 1805-0145 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
--   --   Electric rough in -final 8/30
--   --   CODED LOCKBOX 0202
--   --   Loose screws on decking boards on 2nd and 3rd towers
--   --   Whole house chantilly?
--   --   Silver bedroom light ok? Rest is black. Not completed 5/15
--   --   Remove old sign posts
--   --   New dumpster
--   --   Remove protective film from outside band board
--   --   Ceiling drywall repairs 3/24
--   --   Fridge handles?
--   --   Paint front door
--   --   Caulk in front of tubs Jill has lined up for Monday 6/21
--   --   Touch up paint throughout 5/5
--   --   Drywallers arriving 6/17
--   --   Touch up needed M bath ceiling 6/23
--   --   Drywall touch up, paint touch up Monday, June 28
--   --   Drywall touch up/ paint indicated by blue tape
--   --   Fix showerhead escutcheon to wall
--   --   swap out the current front door lock system with a new system so that we start out with my daughter able to be fully safe
--   --   Raise front door light 18 inches
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       Ordered and set to deliver 1/21
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       In process 5/25
-- -- Electric Rough In (4)       In process 6/17
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Stocked 9/19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Sanding 10/7
-- -- Paint 1 (1)      
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Dec 29th From Kimberly GWB
-- -- Granite Installation (1) *        Feb 8
-- -- Interior Trim - Install (3) *        In process 11/11
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        In process 2/10
-- -- Luxury Vinyl Tile (0)       On site
-- -- Paint 2 (3)       Ready for this anytime
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In process 3/3
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process 3/24.
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       Bathroom vanities not completed/outlet covers needed
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Supplies on site 3/3
-- -- Install Appliances (0) *        5/6?
-- -- Paint 3 (2) *       
-- -- Carpet (2)       NO Carpet
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)       Kate setting this up for the middle of next week
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Friday 25th at 1:00 PM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       6/28/2021 @ 11:30 AM
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       June 30
-- -- Remove Coded Lockbox (0)