- 102  ::  1270 Constitution Court #102
[ BUILD: 1805-0142 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Building Permit (30) *       
Mon    Jan 26      Inspection (Concrete Wall) (1)      
Tue    Jan 27      Inspection (Conduit Under Slab) (1)      
Wed    Jan 28      Inspection (Drain Tile) (0)      
Wed    Jan 28      Settlement Agent Confirmed (0)      
Wed    Jan 28      Verify Window & Roof Structure (0)      
Wed    Jan 28      Patio (0)      
Wed    Jan 28      Rough In Microwave Vent (0)      
Wed    Jan 28      Inspection (Rough In Plumbing) (1)      
Thu    Jan 29      Inspection (Rough In Electric) (1)      
Fri    Jan 30      Inspection (Framing) (1) *       
Mon    Feb 2      Inspection (Deck Piers) (0)      
Mon    Feb 2      Exterior Stone (0)      
Mon    Feb 2      Set Electric Meter (0) *       
Mon    Feb 2      Inspection (Main Water Line) (0)      
Mon    Feb 2      Loan Approval (0)      
Mon    Feb 2      Deed Preparation (0)      
Mon    Feb 2      Mailbox (0)      
Mon    Feb 2      Interior Trim - Paint (1)      
Tue    Feb 3      Ceiling Fans (0)      
Tue    Feb 3      Blower Door Test (1)      
Wed    Feb 4      Inspection (Final HVAC) (1)      
Thu    Feb 5      Inspection (Final Plumbing) (1)      
Fri    Feb 6      Inspection (Final Electric) (1)      
Mon    Feb 9      Stain Hardwood Stairs (1) *       
Tue    Feb 10      Request Trash Tote From POA Manager (0)      
--   --   Handicapped accessible walkway?
--   --   CODED LOCKBOX 0201
--   --   Weather stripping After paint 3
--   --   Bathroom vanity countertops On order per Kimberly-Kimberly sending date-MB in 4/7
--   --   Threshold where shower meets bathroom floor Jill to install
--   --   Guest bathroom top Installed Thursday, 4/15
--   --   Bedroom door needs shaved down 4/17 Trim guys - Courtney will check it
--   --   One closet needs shelving 4/17 Not complete 5/1
--   --   One closet needs shelving 4/17
--   --   Few handles Ron
--   --   White receptacle in kitchen needs grey Jill will tell Harry
--   --   Cracked tub (MB) Jill to schedule
--   --   Adjust front door threshold
--   --   Patch hole at bathroom light
--   --   Sweep out debris and repair and secure shower to floor
--   --   Cut light in over shower
--   --   Patch drywall hole in master bath as well as vent in laundry room In process 4/28
--   --   Swap front door closet shelving with coat closet shelving
--   --   Swap front door closet shelving with coat closet shelving
--   --   Leave construction lockbox
--   --   Leave construction lockbox
--   --   Swap front door closet shelving with coat closet shelving
--   --   Clean outdoor siding
--   --   Cleaning again?
--   --   Shower update
--   --   Hole in back of shower in hall bathroom Jill is scheduling
--   --   Shower grab bar Ron
--   --   Tile shower
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       in process 5/3
-- -- Electric Rough In (4)       In process 6/17
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        stocked 9/19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs final sanding 10/10
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        In process 3/17
-- -- Granite Installation (1) *        Kitchen in 3/21. Vanities are not.
-- -- Interior Trim - Install (3) *        On site 11/18
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        After first week of April
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Agreeable grey is completed 2/24
-- -- Cover Floors (1)       Jill after install
-- -- Deliver Plumbing / Lighting Fixtures (0)       Kate will check on this
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        In process 4/21
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        in process 4/15
-- -- Install Appliances (0) *        Waiting on range plug install from Harry
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Mon, 4/12
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        After Harry finishes
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        5/14
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title
-- -- Remove Coded Lockbox (0)