| Mon | Dec 15 | Ratified Contract? (0) | ||
| Mon | Dec 15 | $2500 Deposit Received (0) | ||
| Mon | Dec 15 | Association Packet Requested (0) | ||
| Mon | Dec 15 | Association Packet Received (0) | ||
| Mon | Dec 15 | Selections Meeting (0) | ||
| Mon | Dec 15 | Selections Sheet Signed (0) | ||
| Mon | Dec 15 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Mon | Dec 15 | Deposit For Upgrades Received (0) | ||
| Mon | Dec 15 | Building Permit (30) * | ||
| Mon | Jan 26 | Inspection (Concrete Wall) (1) | ||
| Tue | Jan 27 | Inspection (Conduit Under Slab) (1) | ||
| Wed | Jan 28 | Inspection (Drain Tile) (0) | ||
| Wed | Jan 28 | Settlement Agent Confirmed (0) | ||
| Wed | Jan 28 | Verify Window & Roof Structure (0) | ||
| Wed | Jan 28 | Patio (0) | ||
| Wed | Jan 28 | Rough In Microwave Vent (0) | ||
| Wed | Jan 28 | Inspection (Rough In Plumbing) (1) | ||
| Thu | Jan 29 | Inspection (Rough In Electric) (1) | ||
| Fri | Jan 30 | Inspection (Framing) (1) * | ||
| Mon | Feb 2 | Inspection (Deck Piers) (0) | ||
| Mon | Feb 2 | Exterior Stone (0) | ||
| Mon | Feb 2 | Set Electric Meter (0) * | ||
| Mon | Feb 2 | Inspection (Main Water Line) (0) | ||
| Mon | Feb 2 | Loan Approval (0) | ||
| Mon | Feb 2 | Deed Preparation (0) | ||
| Mon | Feb 2 | Mailbox (0) | ||
| Mon | Feb 2 | Interior Trim - Paint (1) | ||
| Tue | Feb 3 | Ceiling Fans (0) | ||
| Tue | Feb 3 | Blower Door Test (1) | ||
| Wed | Feb 4 | Inspection (Final HVAC) (1) | ||
| Thu | Feb 5 | Inspection (Final Plumbing) (1) | ||
| Fri | Feb 6 | Inspection (Final Electric) (1) | ||
| Mon | Feb 9 | Stain Hardwood Stairs (1) * | ||
| Tue | Feb 10 | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Handicapped accessible walkway? | ||
| -- | -- | CODED LOCKBOX 0201 | ||
| -- | -- | Weather stripping | After paint 3 | |
| -- | -- | Bathroom vanity countertops | On order per Kimberly-Kimberly sending date-MB in 4/7 | |
| -- | -- | Threshold where shower meets bathroom floor | Jill to install | |
| -- | -- | Guest bathroom top | Installed Thursday, 4/15 | |
| -- | -- | Bedroom door needs shaved down 4/17 | Trim guys - Courtney will check it | |
| -- | -- | One closet needs shelving 4/17 | Not complete 5/1 | |
| -- | -- | One closet needs shelving 4/17 | ||
| -- | -- | Few handles | Ron | |
| -- | -- | White receptacle in kitchen needs grey | Jill will tell Harry | |
| -- | -- | Cracked tub (MB) | Jill to schedule | |
| -- | -- | Adjust front door threshold | ||
| -- | -- | Patch hole at bathroom light | ||
| -- | -- | Sweep out debris and repair and secure shower to floor | ||
| -- | -- | Cut light in over shower | ||
| -- | -- | Patch drywall hole in master bath as well as vent in laundry room | In process 4/28 | |
| -- | -- | Swap front door closet shelving with coat closet shelving | ||
| -- | -- | Swap front door closet shelving with coat closet shelving | ||
| -- | -- | Leave construction lockbox | ||
| -- | -- | Leave construction lockbox | ||
| -- | -- | Swap front door closet shelving with coat closet shelving | ||
| -- | -- | Clean outdoor siding | ||
| -- | -- | Cleaning again? | ||
| -- | -- | Shower update | ||
| -- | -- | Hole in back of shower in hall bathroom | Jill is scheduling | |
| -- | -- | Shower grab bar | Ron | |
| -- | -- | Tile shower | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Order Appliances (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | in process 5/3 | |
| -- | -- | Electric Rough In (4) | In process 6/17 | |
| -- | -- | Inspection (Rough In HVAC) (1) | ||
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | stocked 9/19 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | Needs final sanding 10/10 | |
| -- | -- | Paint 1 (1) | ||
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | In process 3/17 | |
| -- | -- | Granite Installation (1) * | Kitchen in 3/21. Vanities are not. | |
| -- | -- | Interior Trim - Install (3) * | On site 11/18 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | After first week of April | |
| -- | -- | Luxury Vinyl Tile (0) | ||
| -- | -- | Paint 2 (3) | Agreeable grey is completed 2/24 | |
| -- | -- | Cover Floors (1) | Jill after install | |
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | Kate will check on this | |
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | ||
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | In process 4/21 | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | in process 4/15 | |
| -- | -- | Install Appliances (0) * | Waiting on range plug install from Harry | |
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | Mon, 4/12 | |
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | After Harry finishes | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | ||
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | ||
| -- | -- | Buyer Walk Through (1) * | 5/14 | |
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Closing (1) | West View Title | |
| -- | -- | Remove Coded Lockbox (0) | ||