- 103  ::  1270 Constitution Court #103
[ BUILD: 1805-0143 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
--   --   Exposed black area on back corner of home-landscaping repair? 10/14
--   --   CODED LOCKBOX 0103
--   --   Molding needed in archway 12/16
--   --   Trim/doors need painting 1/6
--   --   Drywall repair laundry room 2/27 In process 3/10
--   --   Need side sliding door keys
--   --   Leak at air handler? Alex will take care of it
--   --   Finish rear of the building landscaping?
--   --   Stove plug needed
--   --   Side splash incorrect hall bath?
--   --   Final drywall finishing needed in laundry room
--   --   Fridge w missing handles is located here
--   --   Dead landscaping 5/19 Tom will tell them
--   --   Master bath countertops needed
--   --   Patch holes in closet In process
--   --   Touch up paint
--   --   Lightbulbs Jill
--   --   Covers for MB light Jill
--   --   Cable
--   --   Cable cover on wall Jill will contact Lumos
--   --   shower rod in master bath needs installed~missing one end piece Jill
--   --   take robe hook off the wall outside shower~owner does not want it Jill will tell Majer
--   --   put ring around the sprinkler in the laundry room ceiling Tom-ring is on top of laundry shelving. Just needs installed 6/5
--   --   garbage disposal is not wired Jill will remind Harry- seems to work ok 6/5
--   --   caulk around the sprinkler in living room ceiling Jill will tell Majer
--   --   splash block outside under the master bedroom window is tilted the wrong way~need to build it up a little in the back still needs to be adjusted as of 6/9
--   --   caulk around the pipes going in the ceiling in the mechanical room Jill will tell Majer
--   --  
--   --   Touch up paint at area where robe hook was located as of 6/9
--   --   Repair loud garbage disposal as of 6/9
--   --   Sweep or mop floors as of 6/9
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       One full set on site 3/10
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 4/29
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       In process 7/15
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Stocked 9/19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        in process 10/31
-- -- Paint 1 (1)      
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Installation May 13
-- -- Granite Installation (1) *        Partially complete 5/15
-- -- Interior Trim - Install (3) *       
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Mon, May 17
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)      
-- -- Cover Floors (1)       Jill will take care of it
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Wed, May 19?
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       Partially complete 5/31
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        All on site 5/15
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        6/1 afternoon
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       June 11th at 11AM
-- -- Buyer Walk Through (1)       Wed, June 2
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       June 11th at 11AM
-- -- Remove Coded Lockbox (0)