ADDR
CONGERS-2 - 39 :: 1623 Palomino Trail
[ BUILD:
20241830
]
CRITICAL PATH
|
INSPECTIONS
|
FLOOR PLANS
|
SELECTIONS
|
SPECS
|
CHANGES
|
NHS
view photo archive
--
--
Closing complete on house to be sold?
scheduled to close Nov 30
--
--
Must close by 1031 deadline!
Thu
Nov 14
Selections Meeting
(0)
Thu
Nov 14
Selections Sheet Signed
(0)
Thu
Nov 14
Amendment for Upgrades (B,S,L,T,BCP)
(0)
Thu
Nov 14
Deposit For Upgrades Received
(0)
Thu
Nov 14
Order Windows & Doors
(0)
Thu
Nov 14
Settlement Agent Confirmed
(0)
Thu
Nov 14
Framing I
(9)
Wed
Nov 27
Order Steps
(0)
Wed
Nov 27
Order Tubs / Showers
(0)
Wed
Nov 27
Framing II
(8)
Mon
Dec 9
Framing III
(8)
Thu
Dec 19
Verify Window & Roof Structure
(0)
Thu
Dec 19
Install Stairs
(0)
Thu
Dec 19
Windows & Doors
(0)
Thu
Dec 19
House Number and Status in Window
(0)
Thu
Dec 19
Roofing
(0)
Thu
Dec 19
Order Cabinets
(0)
Thu
Dec 19
Order Appliances
(0)
Thu
Dec 19
Deck
(0)
Thu
Dec 19
Gutters
(0)
Thu
Dec 19
Driveway
(0)
Thu
Dec 19
Patio
(0)
Thu
Dec 19
Privacy Divider / Fence
(0)
Thu
Dec 19
Sod / Seed / Landscaping
(0)
Thu
Dec 19
HVAC Rough In
(4)
Wed
Dec 25
Inspection (Rough In HVAC)
(1)
Thu
Dec 26
Rough In Microwave Vent
(0)
Thu
Dec 26
Plumbing Rough In
(4)
Wed
Jan 1
Inspection (Rough In Plumbing)
(1)
Thu
Jan 2
Electric Rough In
(4)
Wed
Jan 8
Inspection (Rough In Electric)
(1)
Thu
Jan 9
Inspection (Deck Piers)
(0)
Thu
Jan 9
Inspection (Framing)
(1)
Fri
Jan 10
Exterior Vinyl
(0)
Fri
Jan 10
Exterior Stone
(0)
Fri
Jan 10
Insulation
(2)
Tue
Jan 14
Inspection (Insulation)
(1)
Wed
Jan 15
Inspection (Electric Service)
(0)
Wed
Jan 15
Set Electric Meter
(0)
Wed
Jan 15
Inspection (Main Sewer Line)
(0)
Wed
Jan 15
Inspection (Main Water Line)
(0)
Wed
Jan 15
Order Interior Doors & Trim
(0)
Wed
Jan 15
Drywall (Hang)
(4)
Tue
Jan 21
Loan Approval
(0)
Tue
Jan 21
Deed Preparation
(0)
Tue
Jan 21
Drywall (Tape, Block, Skim, Sand)
(6)
Wed
Jan 29
Paint 1
(1)
Thu
Jan 30
Garage Door
(0)
Thu
Jan 30
House Numbers
(0)
Thu
Jan 30
Mailbox
(0)
Thu
Jan 30
Cabinet Installation
(2)
Mon
Feb 3
Granite Installation
(1)
Tue
Feb 4
Interior Trim - Install
(3)
Fri
Feb 7
Order Plumbing / Lighting Fixtures
(0)
Fri
Feb 7
Interior Trim - Paint
(1)
Mon
Feb 10
Luxury Vinyl Plank
(3)
Thu
Feb 13
Luxury Vinyl Tile
(0)
Thu
Feb 13
Paint 2
(3)
Tue
Feb 18
Cover Floors
(1)
Wed
Feb 19
Deliver Plumbing / Lighting Fixtures
(0)
Wed
Feb 19
Shoe Moulding
(0)
Wed
Feb 19
Shelving, Door Knobs, Fire Extinguisher
(0)
Wed
Feb 19
Install Coded Lockbox (add extra keys)
(0)
Wed
Feb 19
Pay Water / Sewer Taps
(0)
Wed
Feb 19
Set Water Meter
(0)
Wed
Feb 19
Electric Trim Out
(3)
Mon
Feb 24
Ceiling Fans
(0)
Mon
Feb 24
HVAC Trim Out
(1)
Tue
Feb 25
Blower Door Test
(1)
Wed
Feb 26
Plumbing Trim Out
(2)
Fri
Feb 28
Install Appliances
(0)
Fri
Feb 28
Paint 3
(2)
Tue
Mar 4
Carpet
(2)
Thu
Mar 6
Appraiser Confirms Construction Completion
(0)
Thu
Mar 6
Inspection (Final HVAC)
(1)
Fri
Mar 7
Inspection (Final Plumbing)
(1)
Mon
Mar 10
Inspection (Final Electric)
(1)
Tue
Mar 11
Inspection (Final Building)
(2)
Thu
Mar 13
Pre Walk Through
(0)
Thu
Mar 13
Stain Hardwood Stairs
(1)
Fri
Mar 14
Cleaning
(1)
Mon
Mar 17
Certificate of Occupancy
(1)
Tue
Mar 18
C.O. to Lender
(0)
Tue
Mar 18
Schedule Closing
(0)
Tue
Mar 18
Buyer Walk Through
(1)
Wed
Mar 19
Payment for Upgrades
(0)
Wed
Mar 19
Keys to Settlement Agent
(0)
Wed
Mar 19
Review Settlement Statement
(0)
Wed
Mar 19
Jerry Signs Closing Documents
(0)
Wed
Mar 19
Request Trash Tote From POA Manager
(0)
Wed
Mar 19
Closing
(1)
Thu
Mar 20
Remove Coded Lockbox
(0)
--
--
Ratified Contract?
(0) 11.02.2024
--
--
$2500 Deposit Received
(0) 11.02.2024
--
--
Association Packet Requested
(0) 11.02.2024
--
--
Association Packet Received
(0) 11.08.2024
--
--
Building Permit
(30) 10.07.2024
--
--
Order Roof & Floor Trusses
(1) 10.17.2024
--
--
Stake Out Home
(1) 10.14.2024
--
--
Excavate
(2) 10.21.2024
--
--
Inspection (Footers)
(1) 10.21.2024
--
--
Inspection (Concrete Wall)
(1) 10.21.2024
--
--
Pour Footers
(1) 10.21.2024
--
--
Set Forms
(2) 11.13.2024
--
--
Pour Foundation Walls
(1) 11.13.2024
--
--
Plumb Slab
(2) 11.13.2024
--
--
Inspection (Plumbing Under Slab)
(1) 11.13.2024
--
--
Inspection (Conduit Under Slab)
(1) 11.13.2024
--
--
Prepare Slab
(1) 11.13.2024
--
--
Inspection (Slab)
(1) 11.13.2024
--
--
Inspection (Drain Tile)
(0) 11.13.2024
--
--
Pour Slab
(1) 11.13.2024