CONGERS-2 - 22  ::  1429 Derby Drive
[ BUILD: 20242227 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Order Roof & Floor Trusses (1)      
Fri    Nov 29      Order Windows & Doors (0)      
Fri    Nov 29      Stake Out Home (1)      
Mon    Dec 2      Excavate (2)      
Wed    Dec 4      Inspection (Footers) (1)      
Thu    Dec 5      Inspection (Concrete Wall) (1)      
Fri    Dec 6      Pour Footers (1)      
Mon    Dec 9      Set Forms (2)      
Wed    Dec 11      Pour Foundation Walls (1)      
Thu    Dec 12      Plumb Slab (2)      
Mon    Dec 16      Inspection (Plumbing Under Slab) (1)      
Tue    Dec 17      Inspection (Conduit Under Slab) (1)      
Wed    Dec 18      Prepare Slab (1)      
Thu    Dec 19      Inspection (Slab) (1)      
Fri    Dec 20      Inspection (Drain Tile) (0)      
Fri    Dec 20      Pour Slab (1) *       
Mon    Dec 23      Settlement Agent Confirmed (0)      
Mon    Dec 23      Framing I (9)      
Fri    Jan 3      Order Steps (0)      
Fri    Jan 3      Order Tubs / Showers (0)      
Fri    Jan 3      Framing II (8)      
Wed    Jan 15      Framing III (8) *       
Mon    Jan 27      Verify Window & Roof Structure (0)      
Mon    Jan 27      Install Stairs (0)      
Mon    Jan 27      Windows & Doors (0)      
Mon    Jan 27      House Number and Status in Window (0)      
Mon    Jan 27      Roofing (0)      
Mon    Jan 27      Order Cabinets (0)      
Mon    Jan 27      Order Appliances (0)      
Mon    Jan 27      Deck (0)      
Mon    Jan 27      Gutters (0)      
Mon    Jan 27      Driveway (0)      
Mon    Jan 27      Patio (0)      
Mon    Jan 27      Privacy Divider / Fence (0)      
Mon    Jan 27      Sod / Seed / Landscaping (0)      
Mon    Jan 27      HVAC Rough In (4)      
Fri    Jan 31      Inspection (Rough In HVAC) (1)      
Mon    Feb 3      Rough In Microwave Vent (0)      
Mon    Feb 3      Plumbing Rough In (4)      
Fri    Feb 7      Inspection (Rough In Plumbing) (1)      
Mon    Feb 10      Electric Rough In (4)      
Fri    Feb 14      Inspection (Rough In Electric) (1)      
Mon    Feb 17      Inspection (Deck Piers) (0)      
Mon    Feb 17      Inspection (Framing) (1)      
Tue    Feb 18      Exterior Vinyl (0) *       
Tue    Feb 18      Exterior Stone (0)      
Tue    Feb 18      Insulation (2)      
Thu    Feb 20      Inspection (Insulation) (1)      
Fri    Feb 21      Inspection (Electric Service) (0)      
Fri    Feb 21      Set Electric Meter (0)      
Fri    Feb 21      Inspection (Main Sewer Line) (0)      
Fri    Feb 21      Inspection (Main Water Line) (0)      
Fri    Feb 21      Order Interior Doors & Trim (0)      
Fri    Feb 21      Drywall (Hang) (4) *       
Thu    Feb 27      Loan Approval (0)      
Thu    Feb 27      Deed Preparation (0)      
Thu    Feb 27      Drywall (Tape, Block, Skim, Sand) (6) *       
Fri    Mar 7      Paint 1 (1)      
Mon    Mar 10      Garage Door (0)      
Mon    Mar 10      House Numbers (0)      
Mon    Mar 10      Mailbox (0)      
Mon    Mar 10      Cabinet Installation (2) *       
Wed    Mar 12      Granite Installation (1) *       
Thu    Mar 13      Interior Trim - Install (3)      
Tue    Mar 18      Order Plumbing / Lighting Fixtures (0)      
Tue    Mar 18      Interior Trim - Paint (1)      
Wed    Mar 19      Luxury Vinyl Plank (3) *       
Mon    Mar 24      Luxury Vinyl Tile (0)      
Mon    Mar 24      Paint 2 (3)      
Thu    Mar 27      Cover Floors (1)      
Fri    Mar 28      Deliver Plumbing / Lighting Fixtures (0)      
Fri    Mar 28      Shoe Moulding (0)      
Fri    Mar 28      Shelving, Door Knobs, Fire Extinguisher (0)      
Fri    Mar 28      Install Coded Lockbox (add extra keys) (0)      
Fri    Mar 28      Pay Water / Sewer Taps (0)      
Fri    Mar 28      Set Water Meter (0)      
Fri    Mar 28      Electric Trim Out (3)      
Wed    Apr 2      Ceiling Fans (0)      
Wed    Apr 2      HVAC Trim Out (1)      
Thu    Apr 3      Blower Door Test (1)      
Fri    Apr 4      Plumbing Trim Out (2)      
Tue    Apr 8      Install Appliances (0) *       
Tue    Apr 8      Paint 3 (2) *       
Thu    Apr 10      Carpet (2)      
Mon    Apr 14      Appraiser Confirms Construction Completion (0)      
Mon    Apr 14      Inspection (Final HVAC) (1)      
Tue    Apr 15      Inspection (Final Plumbing) (1)      
Wed    Apr 16      Inspection (Final Electric) (1)      
Thu    Apr 17      Inspection (Final Building) (2) *       
Mon    Apr 21      Pre Walk Through (0)      
Mon    Apr 21      Stain Hardwood Stairs (1)      
Tue    Apr 22      Cleaning (1)      
Wed    Apr 23      Certificate of Occupancy (1) *       
Thu    Apr 24      C.O. to Lender (0)      
Thu    Apr 24      Schedule Closing (0)      
Thu    Apr 24      Buyer Walk Through (1)      
Fri    Apr 25      Payment for Upgrades (0)      
Fri    Apr 25      Keys to Settlement Agent (0)      
Fri    Apr 25      Review Settlement Statement (0)      
Fri    Apr 25      Jerry Signs Closing Documents (0)      
Fri    Apr 25      Request Trash Tote From POA Manager (0)      
Fri    Apr 25      Closing (1)      
Mon    Apr 28      Remove Coded Lockbox (0)      
-- -- Ratified Contract? (0)  11.26.2024    
-- -- Association Packet Requested (0)  11.26.2024    
-- -- Building Permit (30)  11.21.2024