CONGERS-2 - 5  ::  1240 Cottage Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Mini-split
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Order Tubs / Showers (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Install Stairs (0)      
Mon    Dec 2      House Number and Status in Window (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Garage Door (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Deliver Plumbing / Lighting Fixtures (0)      
Fri    Dec 6      Shoe Moulding (0)      
Fri    Dec 6      Set Water Meter (0)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Paint 3 (2) *       
Wed    Dec 11      Inspection (Final HVAC) (1)      
Thu    Dec 12      Inspection (Final Plumbing) (1)      
Fri    Dec 13      Inspection (Final Electric) (1)      
Mon    Dec 16      Stain Hardwood Stairs (1)      
Tue    Dec 17      Schedule Closing (0)      
Tue    Dec 17      Payment for Upgrades (0)      
Tue    Dec 17      Keys to Settlement Agent (0)      
Tue    Dec 17      Review Settlement Statement (0)      
Tue    Dec 17      Jerry Signs Closing Documents (0)      
Tue    Dec 17      Request Trash Tote From POA Manager (0)      
Tue    Dec 17      Closing (1)      
Wed    Dec 18      Remove Coded Lockbox (0)      
--   --   Schedule framing and electrical walk through with buyer
--   --   Get price for painting one room with different color trim
--   --   Hardwood treads
--   --   Final HVAC work condensate line, line set for mini split
--   --   Buyer has told lender the house will be complete on June 5
--   --   Beam at back porch
--   --   Please cover tub and shower before drywall
--   --   Closet in bonus room?
--   --   Working on retaining wall this morning
--   --   Please cover granite
--   --   Finish hardwood Memorial Day
--   --   Trash and Parking Issues
--   --   Garage Door Installation
--   --   Siding and J Channel May 22: This week
--   --   CO to Angel Fitzgerald (lender)
--   --   Asphalt driveway Tom following up with Channon
--   --   Time to switch out dining light
--   --   Transition strips between hardwood and ceramic and several locations Eric
--   --   Staining steps Isaac - Fri, Jun 1
--   --   Paint access panel in up closet bedroom Isaac
--   --   Bath hardware in up hall bath Ron
--   --   Set door into attic in up bedroom closet Tom
--   --   Shoe mold nail holes fill and paint
--   --   Paint front door Isaac
--   --   Stain Steps Mon, Jun 5
--   --   Doorway to storage over garage
--   --   Need Touch Up Kit Kate emailed Gabby
--   --   Excess Glue in Master Bedroom and glue in master shower Kate emailed Eric
--   --   Move Robe hook, raise shelf in laundry for raised washer/dryer, add hardware to bypass pantry doors in kitchen Ron- Monday
--   --   Fix trim ( gap between casing and floor) on the bottom of many of the doors Fixed-needs caulk and paint
--   --   Transition strip between up hall bath and floor has a gap Eric- still needs to be secured
--   --   Extend and bury drain pipe in front yard Osbaldo
--   --   Finish installing mini split Ronnie- ordering part
--   --   Drywall repair - wall above door to bonus room and both up bedroom ceilings McClung- Friday 6/8
--   --   Missing Tube Light in up Hall Closet Tom/Osbaldo
--   --   Cover Up Bedroom Floors to protect from drywall repair Osbaldo ( first thing Friday morning 6/8)
--   --   Paint touch up (finish risers and spindles, blue tape areas, check back of master closet, paint all white closets Isaac- Friday 6/8
--   --   Wash off siding Osbaldo
--   --   BUYERS WANT TO CLOSE TUESDAY?????
--   --   2 additional areas marked with blue tape in garage Tom/Osbaldo
--   --   Floor touch ups in room over garage Osbaldo
--   --   Take up paper- mop floors one more time
--   --   Nail pops to be filled in trim around window at front door
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       Dec 13
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0)       Mon, Feb 13
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Mostly done
-- -- Inspection (Rough In HVAC) (1)       Inspections 3/7
-- -- Plumbing Rough In (4)       Starting 2/20/2017
-- -- Electric Rough In (4)       3/5 - in process
-- -- Exterior Vinyl (0) *        In process
-- -- Insulation (2)       Nearly complete
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Harry needs to mount the meter base;
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Ordering when drywall begins
-- -- Drywall (Hang) (4) *        1/27 beginning today
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Sanding- will be complete by 4/11
-- -- Paint 1 (1)       Wednesday 4/12
-- -- House Numbers (0)       Osbaldo
-- -- Cabinet Installation (2) *        4/17 installation nearly complete
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       4/24- trim in process
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       5/8 complete upstairs bathroom
-- -- Paint 2 (3)      
-- -- Cover Floors (1)       5/15-Today- big job need to finish master
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Ron
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       Harry- Thursday-Friday 6/1-6/2
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Mon, June 12
-- -- Pre Walk Through (0)       Wednesday morning
-- -- Cleaning (1)       Tuesday - Wednesday
-- -- Certificate of Occupancy (1) *        NEED ASAP
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       4PM on Wednesday